In 20x1, ABC Co. was contracted to build a railroad. The contract price is equal to the construction costs incurred plus 20% thereof. However, if the project is completed within 4 years, ABC will receive an additional payment of P200,000. Information on the project is shown below: 20x1 20x2 Costs incurred to date Estimated costs to complete 2,400,000 3,600,000 4,575,000 1,525,000 20x3 6,125,000 125,000 In 20x1 and 20x2, it was not highly probable that the project will be completed on time. However, in 20x3, ABC assessed that the project will be completed earlier than originally expected and thus it is now highly probable that the incentive payment will be received.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Questions: 1. How much revenue is recognized in the contract in 20x3? 2. How much profit is recognized in the contract in 20x3?
In 20x1, ABC Co. was contracted to build a railroad. The contract price is equal to the construction
costs incurred plus 20% thereof. However, if the project is completed within 4 years, ABC will receive
an additional payment of P200,000. Information on the project is shown below:
20x1
20x2
Costs incurred to date
Estimated costs to complete
2,400,000
3,600,000
4,575,000
1,525,000
20x3
6,125,000
125,000
In 20x1 and 20x2, it was not highly probable that the project will be completed on time. However, in
20x3, ABC assessed that the project will be completed earlier than originally expected and thus it is
now highly probable that the incentive payment will be received.
Transcribed Image Text:In 20x1, ABC Co. was contracted to build a railroad. The contract price is equal to the construction costs incurred plus 20% thereof. However, if the project is completed within 4 years, ABC will receive an additional payment of P200,000. Information on the project is shown below: 20x1 20x2 Costs incurred to date Estimated costs to complete 2,400,000 3,600,000 4,575,000 1,525,000 20x3 6,125,000 125,000 In 20x1 and 20x2, it was not highly probable that the project will be completed on time. However, in 20x3, ABC assessed that the project will be completed earlier than originally expected and thus it is now highly probable that the incentive payment will be received.
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education