In 20x1, ABC Co. enters into a contract to construct a building for a customer. ABC identifies its performance obligation to be satisfied over time. ABC measures its progress on the contract based on costs incurred. The contract price is P20,000,000. ABC has an unconditional right to all billings made in accordance with the billing schedule stated in the contract. Information on the construction is as follows: 20x1 20x2 20x3 Contract costs incurred per year Billings per year Collections on billings 8,160,000 7,320,000 1,920,000 10,000,000 7,000,000 3,000,000 9,500,000 6,650,000 3,850,000 per year Estimated costs to complete (at each year-end) 8,840,000 1,720,000 How much profit is recognized on the contract in 20x3?

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
In 20x1, ABC Co. enters into a contract to construct a building
for a customer. ABC identifies its performance obligation to be
satisfied over time. ABC measures its progress on the
contract based on costs incurred. The contract price is
P20,000,000. ABC has an unconditional right to all billings
made in accordance with the billing schedule stated in the
contract. Information on the construction is as follows:
20x1
20x2
20x3
Contract costs incurred
per year
Billings per year
Collections on billings
per year
Estimated costs to
8,160,000 7,320,000
1,920,000
10,000,000 7,000,000 3,000,000
9,500,000 6,650,000 3,850,000
complete (at each
year-end)
8,840,000 1,720,000
How much profit is recognized on the contract in 20x3?
Transcribed Image Text:In 20x1, ABC Co. enters into a contract to construct a building for a customer. ABC identifies its performance obligation to be satisfied over time. ABC measures its progress on the contract based on costs incurred. The contract price is P20,000,000. ABC has an unconditional right to all billings made in accordance with the billing schedule stated in the contract. Information on the construction is as follows: 20x1 20x2 20x3 Contract costs incurred per year Billings per year Collections on billings per year Estimated costs to 8,160,000 7,320,000 1,920,000 10,000,000 7,000,000 3,000,000 9,500,000 6,650,000 3,850,000 complete (at each year-end) 8,840,000 1,720,000 How much profit is recognized on the contract in 20x3?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Intangible assets
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education