In 2019, Tarlo Company agrees to construct a highway for Brice County over a 3-year period (2019 through 2021). The contract price is $1,200,000, and the construction costs (both actual and estimated) total $705,000 for the 3 years. Tarlo's estimate of progress toward satisfaction of the performance obligation at the end of each year is as follows: 2019, 20%; 2020, 75%; 2021, 100%. Required: 1. Prepare a schedule showing the amount of gross profit that Tarlo recognizes each year assuming the performance obligation is determined to be satisfied over time. Tarlo Company Gross Profit: Percentage-of Completion Method 2019 through 2021 Amount 2019 $ 2020 2021 Total gross profit $ 2. Prepare a schedule showing the amount of gross profit that Tarlo recognizes each year assuming the performance obligation is satisfied at a point in time. If an amount is zero, enter "0". Tarlo Company Gross Profit: Completed-Contract Method 2019 through 2021 Amount 2019 $ 2020 2021 Total gross profit $
In 2019, Tarlo Company agrees to construct a highway for Brice County over a 3-year period (2019 through 2021). The contract price is $1,200,000, and the construction costs (both actual and estimated) total $705,000 for the 3 years. Tarlo's estimate of progress toward satisfaction of the performance obligation at the end of each year is as follows: 2019, 20%; 2020, 75%; 2021, 100%.
Required:
1. Prepare a schedule showing the amount of gross profit that Tarlo recognizes each year assuming the performance obligation is determined to be satisfied over time.
Tarlo Company | |
Gross Profit: Percentage-of Completion Method | |
2019 through 2021 | |
Amount | |
2019 | $ |
2020 | |
2021 | |
Total gross profit | $ |
2. Prepare a schedule showing the amount of gross profit that Tarlo recognizes each year assuming the performance obligation is satisfied at a point in time. If an amount is zero, enter "0".
Tarlo Company | |
Gross Profit: Completed-Contract Method | |
2019 through 2021 | |
Amount | |
2019 | $ |
2020 | |
2021 | |
Total gross profit | $ |
![](/static/compass_v2/shared-icons/check-mark.png)
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)