IDENTIFY 1. Variation orders to the contract may be _________ wherein the revised contract amount after applying a variation to the scope of works will have an additional. 2. Variation orders to the contract may be _________ wherein the revised contract amount after applying a variation to the scope of works will not change it. 3. These are the costs that are not physically seen while implementing the project.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter8: Pricing Generally
Section: Chapter Questions
Problem 5RQ
icon
Related questions
Question

IDENTIFY
1. Variation orders to the contract may be _________ wherein the revised
contract amount after applying a variation to the scope of works will have
an additional.
2. Variation orders to the contract may be _________ wherein the revised
contract amount after applying a variation to the scope of works will not
change it.
3. These are the costs that are not physically seen while implementing the
project.

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Types of contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,