Id ahor LS F 1. NI LF art 10 10 0 74 F 1721 23 13 76 129 I 2536 C 4 7 4 0 11 12 14 23 3 26 160 16 1231 26 73 23 26 G 76715 231123 K 1 10 27 26 13 131 430 123 026 R 2 528 267330 J N 32 433 36 37 0 32 5 37 0 32 137 T 37 2 37 P 39 0 39 26 626 D 32 5 32 032 37 32 031 Q 32 433 36 37 S 26433 30 737 "Alright. We need to start immediately, no time for delay. Use Monday September 30, 2024, as a starting point" "Bossman, do we need to work weekends and holidays to knock this thing out? I have some things planned for the weekends coming up and Thanksgiving..' 01 "No, we don't need to extend resources for that. No weekends or holidays, standard 5 day work week should do it. Well, we will certainly have to start with SITEWORK, and this will take 4 days probably" "After that, the UNDERGROUND UTILITIES can start, and I know we can knock those out in 12 days" "Since we are talking about the outside work, we would have to include 4 days for LANDSCAPING before we CLOSEOUT THE PROJECT" "Right, but we can't start the LANDSCAPING until EXTERIOR PAINTING is complete" "Duh, the UNDERGROUND UTILITIES comes before LANDSCAPING too, boss!" "How much time will we need for EXTERIOR PAINTING?" "5 days" "Okay, but we will have to complete the EXTERIOR SIDING and FINISH ROOF before then" "Yep, but let's get back to the beginning. The ROUGH PLUMBING should take 12 days, and needs to start 5 days after FORM/POUR SLAB starts, which will take at least 7 days to complete" "Do we have to wait until the UNDERGROUND UTILITIES are complete before we FORM/POUR SLAB?" "No, FORM/POUR can start right after SITEWORK, and we will have to wait until the slab is complete before starting to FRAME WALLS" "FRAME WALLS is crucial, let's put 5 days for that. Its completion allow ROUGH ELECTRIC, FRAME ROOF, and the WINDOWS/DOORS to start" "Okay, so let's say 7 days for ROUGH ELECTRIC, 10 days to hang WINDOWS/DOORS and the carpenters can FRAME ROOF in 7 days" "If the boys can frame the roof in 7 days, surely the roofers can FINISH ROOF right after that in 3 days as well" "Yep, FRAME ROOF will allow ROUGH MECHANICAL to start, which will take every bit of 5 days. ROUGH MECHANICAL cannot start until the UNDERGROUND UTILITIES are done either" "EXTERIOR SIDING can start after the WINDOWS/DOORS, and should take 5 days to complete" "Slow down boys, make sure you don't start the 6 days worth of DRYWALL until ROUGH MECHANICAL is complete, and Bubba - make sure they complete the FINISH ROOF first before DRYWALL starts this time!" "10-4 Boss" "INSULATION might take 3 days, but needs to wait on ROUGH ELECTRIC, ROUGH MECHANICAL, and ROUGH PLUMBING to be complete before starting, but should be complete before DRYWALL is complete "We need to start the ROUGH ELECTRIC as soon as possible, but after UNDERGROUND UTILITIES" "Great, so let's have 4 days for FINISH ELECTRIC, and 5 days each for FINISH PLUMBING, and FINISH MECHANICAL, and know that all three need DRYWALL to be complete before starting" "Correct, but don't forget about INTERIOR PAINT, which needs 4 days to complete, and needs to happen after DRYWALL and before FINISH ELECTRIC" "That should do it! Make sure that we have 2 days for PROJECT CLOSEOUT after the 3 FINISH MEP activities and LANDSCAPING to tie up any loose ends" "Sounds good. Great work boys!" 3

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

a. What activities make up the critical path? 
b. When is the proposed finish date? 
c. What are two near-critical activities? 
2 d. If the Architect changes their mind, and the exterior siding material is delayed and does not arrive until Wednesday, November 6, 2024, causing this to be the earliest starting date for the activity, does this impact the finish date listed in question b.? How do you know?
e. What is the new revised finish date if the carpenters that are responsible for the exterior siding cannot work the week of the 4th of November, assuming the material is delayed, and could only start back on Tuesday, November 12th? How do you know? f. If the insulation material is delayed and does not arrive until Tuesday, November 12th, 2024, causing this to be the earliest starting date for the activity, does this impact the finish date listed in question b.? (ignore previous delays in questions d. and e.) How do you know? g. What is the new revised finish date if the insulators cannot work the week of the 11th of November, assuming material is delayed, and could only start back on Monday, November 18th? How do you know?   h. If the Rough Electric takes 4 additional workdays, does this impact the overall project? If so, by how many days? (ignore d. through g.) i. If Dr. Moore and Dr. Al-Shenawa want to visit the jobsite on Thursday, November 21st, and the day after to play golf with Bubba, and it shuts down all work for both days because Bubba is a big hitter and everybody wants to watch, which activities will be impacted? (ignore d. through h.).   please help answer the questions

Id
ahor LS
F
1. NI
LF
art
10
10
0
74
F
1721
23 13 76
129
I
2536
C
4
7
4
0
11 12 14
23 3 26
160 16
1231
26 73
23
26
G
76715
231123
K
1 10 27
26 13 131
430
123
026
R
2
528
267330
J
N
32 433
36 37
0
32 5
37 0
32
137
T
37
2
37
P
39
0
39
26 626
D
32
5
32 032
37
32
031
Q
32 433
36
37
S
26433
30
737
Transcribed Image Text:Id ahor LS F 1. NI LF art 10 10 0 74 F 1721 23 13 76 129 I 2536 C 4 7 4 0 11 12 14 23 3 26 160 16 1231 26 73 23 26 G 76715 231123 K 1 10 27 26 13 131 430 123 026 R 2 528 267330 J N 32 433 36 37 0 32 5 37 0 32 137 T 37 2 37 P 39 0 39 26 626 D 32 5 32 032 37 32 031 Q 32 433 36 37 S 26433 30 737
"Alright. We need to start immediately, no time for delay. Use Monday September 30,
2024, as a starting point"
"Bossman, do we need to work weekends and holidays to knock this thing out? I have some
things planned for the weekends coming up and Thanksgiving..'
01
"No, we don't need to extend resources for that. No weekends or holidays, standard 5 day
work week should do it. Well, we will certainly have to start with SITEWORK, and this will
take 4 days probably"
"After that, the UNDERGROUND UTILITIES can start, and I know we can knock those out in
12 days"
"Since we are talking about the outside work, we would have to include 4 days for
LANDSCAPING before we CLOSEOUT THE PROJECT"
"Right, but we can't start the LANDSCAPING until EXTERIOR PAINTING is complete"
"Duh, the UNDERGROUND UTILITIES comes before LANDSCAPING too, boss!"
"How much time will we need for EXTERIOR PAINTING?"
"5 days"
"Okay, but we will have to complete the EXTERIOR SIDING and FINISH ROOF before then"
"Yep, but let's get back to the beginning. The ROUGH PLUMBING should take 12 days, and
needs to start 5 days after FORM/POUR SLAB starts, which will take at least 7 days to
complete"
"Do we have to wait until the UNDERGROUND UTILITIES are complete before we
FORM/POUR SLAB?"
"No, FORM/POUR can start right after SITEWORK, and we will have to wait until the slab is
complete before starting to FRAME WALLS"
"FRAME WALLS is crucial, let's put 5 days for that. Its completion allow ROUGH ELECTRIC,
FRAME ROOF, and the WINDOWS/DOORS to start"
"Okay, so let's say 7 days for ROUGH ELECTRIC, 10 days to hang WINDOWS/DOORS and the
carpenters can FRAME ROOF in 7 days"
"If the boys can frame the roof in 7 days, surely the roofers can FINISH ROOF right after
that in 3 days as well"
"Yep, FRAME ROOF will allow ROUGH MECHANICAL to start, which will take every bit of 5
days. ROUGH MECHANICAL cannot start until the UNDERGROUND UTILITIES are done
either"
"EXTERIOR SIDING can start after the WINDOWS/DOORS, and should take 5 days to
complete"
"Slow down boys, make sure you don't start the 6 days worth of DRYWALL until ROUGH
MECHANICAL is complete, and Bubba - make sure they complete the FINISH ROOF first
before DRYWALL starts this time!"
"10-4 Boss"
"INSULATION might take 3 days, but needs to wait on ROUGH ELECTRIC, ROUGH
MECHANICAL, and ROUGH PLUMBING to be complete before starting, but should be
complete before DRYWALL is complete
"We need to start the ROUGH ELECTRIC as soon as possible, but after UNDERGROUND
UTILITIES"
"Great, so let's have 4 days for FINISH ELECTRIC, and 5 days each for FINISH PLUMBING, and
FINISH MECHANICAL, and know that all three need DRYWALL to be complete before
starting"
"Correct, but don't forget about INTERIOR PAINT, which needs 4 days to complete, and
needs to happen after DRYWALL and before FINISH ELECTRIC"
"That should do it! Make sure that we have 2 days for PROJECT CLOSEOUT after the 3
FINISH MEP activities and LANDSCAPING to tie up any loose ends"
"Sounds good. Great work boys!"
3
Transcribed Image Text:"Alright. We need to start immediately, no time for delay. Use Monday September 30, 2024, as a starting point" "Bossman, do we need to work weekends and holidays to knock this thing out? I have some things planned for the weekends coming up and Thanksgiving..' 01 "No, we don't need to extend resources for that. No weekends or holidays, standard 5 day work week should do it. Well, we will certainly have to start with SITEWORK, and this will take 4 days probably" "After that, the UNDERGROUND UTILITIES can start, and I know we can knock those out in 12 days" "Since we are talking about the outside work, we would have to include 4 days for LANDSCAPING before we CLOSEOUT THE PROJECT" "Right, but we can't start the LANDSCAPING until EXTERIOR PAINTING is complete" "Duh, the UNDERGROUND UTILITIES comes before LANDSCAPING too, boss!" "How much time will we need for EXTERIOR PAINTING?" "5 days" "Okay, but we will have to complete the EXTERIOR SIDING and FINISH ROOF before then" "Yep, but let's get back to the beginning. The ROUGH PLUMBING should take 12 days, and needs to start 5 days after FORM/POUR SLAB starts, which will take at least 7 days to complete" "Do we have to wait until the UNDERGROUND UTILITIES are complete before we FORM/POUR SLAB?" "No, FORM/POUR can start right after SITEWORK, and we will have to wait until the slab is complete before starting to FRAME WALLS" "FRAME WALLS is crucial, let's put 5 days for that. Its completion allow ROUGH ELECTRIC, FRAME ROOF, and the WINDOWS/DOORS to start" "Okay, so let's say 7 days for ROUGH ELECTRIC, 10 days to hang WINDOWS/DOORS and the carpenters can FRAME ROOF in 7 days" "If the boys can frame the roof in 7 days, surely the roofers can FINISH ROOF right after that in 3 days as well" "Yep, FRAME ROOF will allow ROUGH MECHANICAL to start, which will take every bit of 5 days. ROUGH MECHANICAL cannot start until the UNDERGROUND UTILITIES are done either" "EXTERIOR SIDING can start after the WINDOWS/DOORS, and should take 5 days to complete" "Slow down boys, make sure you don't start the 6 days worth of DRYWALL until ROUGH MECHANICAL is complete, and Bubba - make sure they complete the FINISH ROOF first before DRYWALL starts this time!" "10-4 Boss" "INSULATION might take 3 days, but needs to wait on ROUGH ELECTRIC, ROUGH MECHANICAL, and ROUGH PLUMBING to be complete before starting, but should be complete before DRYWALL is complete "We need to start the ROUGH ELECTRIC as soon as possible, but after UNDERGROUND UTILITIES" "Great, so let's have 4 days for FINISH ELECTRIC, and 5 days each for FINISH PLUMBING, and FINISH MECHANICAL, and know that all three need DRYWALL to be complete before starting" "Correct, but don't forget about INTERIOR PAINT, which needs 4 days to complete, and needs to happen after DRYWALL and before FINISH ELECTRIC" "That should do it! Make sure that we have 2 days for PROJECT CLOSEOUT after the 3 FINISH MEP activities and LANDSCAPING to tie up any loose ends" "Sounds good. Great work boys!" 3
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning