ICU2 computer (end item) Motherboard (1) Lead time -3 weeks Disk drives (2) Lead time = week Add-in-boards (3) Lead time = 1 week DRAM chips (90) Lead time 2 weeks The NoName Computer Company builds a computer designated model ICU2. It imports the motherboard of the computer from Taiwan, but the company inserts the sockets for the chips and boards in its plant in Lubbock, Texas. Each computer requires a total of 90 dynamic random access memory (DRAM) chips. NoName sells the computers with three add-in boards and two disk-drives. The company purchases both the DRAM chips and the disk drives from an outside supplier. The product structure diagram for the ICU2 computer is shown above. Suppose that the forecasted demands for the computer for week 6 to 11 are 220, 165, 180, 120, 75, 300. The starting inventory of assembled computers in week 6 will be 75, and the production manager anticipated returns of 30 in week 8 and 10 in week 10. Determine the master production schedule (MPS) for the ICU2 computer and answer the following questions. Enter your answers as integer. On-hand inventory for Week 6 Scheduled receipts for Week 9 Scheduled receipts for Week 10 Net predicted demand for Week 6 Net predicted demand for Week 8 Net predicted demand for Week 9 Net predicted demand for Week 10

icon
Related questions
Question
ICU2 computer
(end item)
Motherboard (1)
Lead time -3 weeks
Disk drives (2)
Lead time = week
Add-in-boards (3)
Lead time = 1 week
DRAM chips (90)
Lead time
2 weeks
The NoName Computer Company builds a computer designated model
ICU2. It imports the motherboard of the computer from Taiwan, but the
company inserts the sockets for the chips and boards in its plant in
Lubbock, Texas. Each computer requires a total of 90 dynamic random
access memory (DRAM) chips. NoName sells the computers with three
add-in boards and two disk-drives. The company purchases both the
DRAM chips and the disk drives from an outside supplier. The product
structure diagram for the ICU2 computer is shown above.
Suppose that the forecasted demands for the computer for week 6 to 11
are 220, 165, 180, 120, 75, 300. The starting inventory of assembled
computers in week 6 will be 75, and the production manager anticipated
returns of 30 in week 8 and 10 in week 10.
Determine the master production schedule (MPS) for the ICU2 computer
and answer the following questions. Enter your answers as integer.
On-hand inventory for Week 6
Scheduled receipts for Week 9
Scheduled receipts for Week 10
Net predicted demand for Week 6
Net predicted demand for Week 8
Net predicted demand for Week 9
Net predicted demand for Week 10
Transcribed Image Text:ICU2 computer (end item) Motherboard (1) Lead time -3 weeks Disk drives (2) Lead time = week Add-in-boards (3) Lead time = 1 week DRAM chips (90) Lead time 2 weeks The NoName Computer Company builds a computer designated model ICU2. It imports the motherboard of the computer from Taiwan, but the company inserts the sockets for the chips and boards in its plant in Lubbock, Texas. Each computer requires a total of 90 dynamic random access memory (DRAM) chips. NoName sells the computers with three add-in boards and two disk-drives. The company purchases both the DRAM chips and the disk drives from an outside supplier. The product structure diagram for the ICU2 computer is shown above. Suppose that the forecasted demands for the computer for week 6 to 11 are 220, 165, 180, 120, 75, 300. The starting inventory of assembled computers in week 6 will be 75, and the production manager anticipated returns of 30 in week 8 and 10 in week 10. Determine the master production schedule (MPS) for the ICU2 computer and answer the following questions. Enter your answers as integer. On-hand inventory for Week 6 Scheduled receipts for Week 9 Scheduled receipts for Week 10 Net predicted demand for Week 6 Net predicted demand for Week 8 Net predicted demand for Week 9 Net predicted demand for Week 10
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer