i. Determine the length of the project. ii. What is the project length if all activities are crashed to their minimum? iii. Great Work's will lose $3500 in profit weekly for every week the project is not completed. How many weeks will the project take if they are willing to pay crashing cost as long as it is less than $3,500.00

Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question

Question 1B. Please help Thank you

 

B. Great Works Construction has tendered for another project.
Their preliminary evaluation has shown the following activities and
costing will be necessary for successful completion of this job.
Your analysis will help Great Works decide on whether or not this
project is profitable.
Activity Predecessor
A
B
C
D
E
F
A
A
B, C
C
D, E
Normal
Time (Wks)
9
8
15
5
10
2
Crash
Time (Wks)
6
5
10
3
6
1
Normal
Cost ($)
2,000
2,000
5,000
1,000
10,000
4,000
Crash
Cost ($)
11,000
12,500
25,000
5,000
20,000
9,000
i. Determine the length of the project.
ii. What is the project length if all activities are crashed to their
minimum?
iii. Great Work's will lose $3500 in profit weekly for every week
the project is not completed. How many weeks will the project
take if they are willing to pay crashing cost as long as it is less than
$3,500.00
Transcribed Image Text:B. Great Works Construction has tendered for another project. Their preliminary evaluation has shown the following activities and costing will be necessary for successful completion of this job. Your analysis will help Great Works decide on whether or not this project is profitable. Activity Predecessor A B C D E F A A B, C C D, E Normal Time (Wks) 9 8 15 5 10 2 Crash Time (Wks) 6 5 10 3 6 1 Normal Cost ($) 2,000 2,000 5,000 1,000 10,000 4,000 Crash Cost ($) 11,000 12,500 25,000 5,000 20,000 9,000 i. Determine the length of the project. ii. What is the project length if all activities are crashed to their minimum? iii. Great Work's will lose $3500 in profit weekly for every week the project is not completed. How many weeks will the project take if they are willing to pay crashing cost as long as it is less than $3,500.00
Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Recommended textbooks for you
Advanced Engineering Mathematics
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
Numerical Methods for Engineers
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
Introductory Mathematics for Engineering Applicat…
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
Basic Technical Mathematics
Basic Technical Mathematics
Advanced Math
ISBN:
9780134437705
Author:
Washington
Publisher:
PEARSON
Topology
Topology
Advanced Math
ISBN:
9780134689517
Author:
Munkres, James R.
Publisher:
Pearson,