I need an explanation for part b) of the following questions. Scatter Diagrams and High-Low Cost Estimation From April 1 through October 31, Will County Highway Department hires temporary employees to mow and clean the right-of-way along county roads. The County Road Commissioner has asked you to help her in determining the variable labor cost of mowing and cleaning a mile of road. The following information is available regarding current-year operations: Month Miles Mowed and Cleaned Labor Costs April 350 $12,000 May 300 11,250 June 400 13,500 July 250 8,250 August 375 12,750 September 200 7,500 October 100 7,200 Use the information from the high- and low-volume months to develop a cost-estimating equation for monthly labor costs. Monthly labor costs = Answer   + Answer   X Plot the data on a scatter diagram. Using the information from representative high- and low volume months, use the high-low method to develop a cost-estimating equation for monthly labor costs. Monthly labor costs = Answer   + Answer   X

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question

I need an explanation for part b) of the following questions.

Scatter Diagrams and High-Low Cost Estimation
From April 1 through October 31, Will County Highway Department hires temporary employees to mow and clean the right-of-way along county roads. The County Road Commissioner has asked you to help her in determining the variable labor cost of mowing and cleaning a mile of road. The following information is available regarding current-year operations:

Month Miles Mowed
and Cleaned
Labor
Costs
April 350 $12,000
May 300 11,250
June 400 13,500
July 250 8,250
August 375 12,750
September 200 7,500
October 100 7,200


Use the information from the high- and low-volume months to develop a cost-estimating equation for monthly labor costs.

Monthly labor costs = Answer
 
+ Answer
 
X


Plot the data on a scatter diagram. Using the information from representative high- and low volume months, use the high-low method to develop a cost-estimating equation for monthly labor costs.

Monthly labor costs = Answer
 
+ Answer
 
X


Adjust the equation developed in requirement (b) to incorporate the effect of an anticipated 7 percent increase in wages.

Monthly labor costs = Answer
 
+ Answer
 
X
 
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Total Cost
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education