HW// A man started a new project paying initial payment of 500,000S, then 4 annua payments of 250,000$ starting from the end of 1st year. On the beginning of 4h year he started to gain revenue of 800,000$, his revenue decreased for the next 4 year with arithmetic gradient of 5000$ per year. Then the next 2 years his revenue wa zero respectively, so he decided to make some new changes and he gained a revenu of 400, 000$ at the end of 10 year. Make Cash Flow Diagram After that Calculate the cost of his project and the revenue if the rate of interest for cost was 5% and fo the revenue 8%. Useful Equation: Po= PA +PG + if the series of payment increasing by a constant amount G Po= PA - PG if the series of payment decreasing by a constant amount G
HW// A man started a new project paying initial payment of 500,000S, then 4 annua payments of 250,000$ starting from the end of 1st year. On the beginning of 4h year he started to gain revenue of 800,000$, his revenue decreased for the next 4 year with arithmetic gradient of 5000$ per year. Then the next 2 years his revenue wa zero respectively, so he decided to make some new changes and he gained a revenu of 400, 000$ at the end of 10 year. Make Cash Flow Diagram After that Calculate the cost of his project and the revenue if the rate of interest for cost was 5% and fo the revenue 8%. Useful Equation: Po= PA +PG + if the series of payment increasing by a constant amount G Po= PA - PG if the series of payment decreasing by a constant amount G
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
Please use given equation if you need.
![HW// A man started a new project paying initial payment of 500,000S, then 4 annual
payments of 250,000$ starting from the end of 1st year. On the beginning of 4h year,
he started to gain revenue of 800,000$, his revenue decreased for the next 4 years
with arithmetic gradient of 5000$ per year. Then the next 2 years his revenue was
zero respectively, so he decided to make some new changes and he gained a revenue
of 400, 000S at the end of 10th year. Make Cash Flow Diagram After that Calculate
the cost of his project and the revenue if the rate of interest for cost was 5% and for
the revenue 8%.
Useful Equation:
Po= PA +PG
+ if the series of payment increasing by a constant amount G
Po= PA – PG
+ if the series of payment decreasing by a constant amount G
PA = A[+)"-1]
(1+1)"+t
A-G[;
A=GE-a0-
[(1+i)"–1
(1+)"-1.
P = A
(1+i)"-i.
F = P (1+ i)"
P = F (1+ i)-"
F = A |
[(1+i)".](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F512e5030-22f2-4ade-a7f7-5af7a50734bb%2Fdaf187d6-1664-4a56-b675-6d97b5ad4fa4%2F0ufysg7_processed.jpeg&w=3840&q=75)
Transcribed Image Text:HW// A man started a new project paying initial payment of 500,000S, then 4 annual
payments of 250,000$ starting from the end of 1st year. On the beginning of 4h year,
he started to gain revenue of 800,000$, his revenue decreased for the next 4 years
with arithmetic gradient of 5000$ per year. Then the next 2 years his revenue was
zero respectively, so he decided to make some new changes and he gained a revenue
of 400, 000S at the end of 10th year. Make Cash Flow Diagram After that Calculate
the cost of his project and the revenue if the rate of interest for cost was 5% and for
the revenue 8%.
Useful Equation:
Po= PA +PG
+ if the series of payment increasing by a constant amount G
Po= PA – PG
+ if the series of payment decreasing by a constant amount G
PA = A[+)"-1]
(1+1)"+t
A-G[;
A=GE-a0-
[(1+i)"–1
(1+)"-1.
P = A
(1+i)"-i.
F = P (1+ i)"
P = F (1+ i)-"
F = A |
[(1+i)".
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning