Henkes Corporation bases its predetermined overhead rate on the estimated labor-hours for the upcoming year. At the beginning of the most recently completed year, the company estimated the labor-hours for the upcoming year at 66,000 labor-hours. The estimated variable manufacturing overhead was $8.41 per labor-hour and the estimated total fixed manufacturing overhead was $1,533,180. The actual labor-hours for the year turned out to be 68,400 labor-hours. Required: Compute the company's predetermined overhead rate for the recently completed year.
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
I need all parts of this question answered
Henkes Corporation bases its predetermined
Required:
Compute the company's predetermined overhead rate for the recently completed year.
Predetermined overhead rate is based on the estimated overhead cost and estimated direct labor hours.
Overhead cost is the total of variable and fixed overhead cost.
Step by step
Solved in 2 steps