Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $88,800 Number of moves 4,000 Engineering 117,600 Number of change orders 8,000 Other overhead 174,800 Direct labor hours 46,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning balance $23,400 $19,200 $4,700 $0 Direct materials $5,800 $9,600 $13,400 $10,100 Direct labor cost $950 $1,010 $1,590 $110 Job 13-43 Job 13-44 Job 13-45 Job 13-46 Number of moves 46 46 33 6 Number of change orders 35 37 17 23 Direct labor hours 950 1,010 1,590 110 By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Job Costs Using Activity-Based Costing
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted
information for the year is as follows:
Activity
Cost
Driver
Amount of Driver
Materials handling
$88,800 Number of moves
4,000
Engineering
117,600 Number of change orders
8,000
Other overhead
174,800 Direct labor hours
46,000
Heitger worked on four jobs in July. Data are as follows:
Job 13-43
Job 13-44
Job 13-45
Job 13-46
Beginning balance
$23,400
$19,200
$4,700
$0
Direct materials
$5,800
$9,600
$13,400
$10,100
Direct labor cost
$950
$1,010
$1,590
$110
Job 13-43
Job 13-44
Job 13-45
Job 13-46
Number of moves
46
46
33
Number of change orders
35
37
17
23
Direct labor hours
950
1,010
1,590
110
By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.
Transcribed Image Text:Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $88,800 Number of moves 4,000 Engineering 117,600 Number of change orders 8,000 Other overhead 174,800 Direct labor hours 46,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning balance $23,400 $19,200 $4,700 $0 Direct materials $5,800 $9,600 $13,400 $10,100 Direct labor cost $950 $1,010 $1,590 $110 Job 13-43 Job 13-44 Job 13-45 Job 13-46 Number of moves 46 46 33 Number of change orders 35 37 17 23 Direct labor hours 950 1,010 1,590 110 By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.
1. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent.
Materials handling rate
per move
Engineering rate
per change order
Other overhead rate
per direct labor hour
2. Prepare job-order cost sheets for each job showing all costs through July 31.
When required, round your answers to the nearest dollar. If an amount is zero, enter "0".
Heitger Company
Job-Order Cost Sheets
Job 13-43 Job 13-44 Job 13-45 Job 13-46
Balance, July 1
$4
Direct materials
Direct labor cost
Materials handling
Engineering
Other overhead
Total
3. Calculate the balance in Work in Process on July 31.
Transcribed Image Text:1. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent. Materials handling rate per move Engineering rate per change order Other overhead rate per direct labor hour 2. Prepare job-order cost sheets for each job showing all costs through July 31. When required, round your answers to the nearest dollar. If an amount is zero, enter "0". Heitger Company Job-Order Cost Sheets Job 13-43 Job 13-44 Job 13-45 Job 13-46 Balance, July 1 $4 Direct materials Direct labor cost Materials handling Engineering Other overhead Total 3. Calculate the balance in Work in Process on July 31.
Expert Solution
Step 1

Activity rate = Overhead activity cost / Amount of driver

 

  • Job 13-43 Job 13-44 are sold, so their cost will constitute the cost of goods sold.
  • Job 13-45 and Job 13-46 are still in process, so their cost will constitute the ending WIP.
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education