-> Find the preconsolidation pressure for curve below -> Find Compression Index, (Cc) and Swell Index (Cs) for curve with initial void ratio assumed at = 0.8 -> Find total settlement -> Can 50% Consolidation be achieved in 6 months if total surcharge applied is 2400 psf? CONSOLIDATION TEST - ASTM D2435 Boring / Sample No. B-10/ R-4 Depth: 7.5' - 9' Date 03-18-19 1.00 0.9975 0.9950 0.99 - Natural o Submerged 0.98 0.97 0.96 0.9504 0.95 0.94 0.93 0.92 30.91 9089 0.90 F0.89 Silty Clay Dry Density: 81.3 pcf Initial Water Content: 15.1 % Final Water Content: 24.7 % H,O @ 400 PSF G0.88 0.87 0.86 O 0.8532 0.85 0.84 0.83 08341 0.82 0,8232 0.8136 0.8091 0.81 0.80 100 1000 10000 100000 Vertical Pressure (psf)
-> Find the preconsolidation pressure for curve below -> Find Compression Index, (Cc) and Swell Index (Cs) for curve with initial void ratio assumed at = 0.8 -> Find total settlement -> Can 50% Consolidation be achieved in 6 months if total surcharge applied is 2400 psf? CONSOLIDATION TEST - ASTM D2435 Boring / Sample No. B-10/ R-4 Depth: 7.5' - 9' Date 03-18-19 1.00 0.9975 0.9950 0.99 - Natural o Submerged 0.98 0.97 0.96 0.9504 0.95 0.94 0.93 0.92 30.91 9089 0.90 F0.89 Silty Clay Dry Density: 81.3 pcf Initial Water Content: 15.1 % Final Water Content: 24.7 % H,O @ 400 PSF G0.88 0.87 0.86 O 0.8532 0.85 0.84 0.83 08341 0.82 0,8232 0.8136 0.8091 0.81 0.80 100 1000 10000 100000 Vertical Pressure (psf)
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
![Please explain step by step. Thank you.
-> Find the preconsolidation pressure for curve below
-> Find Compression Index, (Cc) and Swell Index (Cs) for curve with initial void ratio assumed at = 0.8
-> Find total settlement
-> Can 50% Consolidation be achieved in 6 months if total surcharge applied is 2400 psf?
CONSOLIDATION TEST - ASTM D2435
Boring / Sample No.
B-10 / R-4
Depth:
7.5' - 9'
Date
03-18-19
1.00
0.9975
0.9950
0.99
- Natural
o Submerged
0.98
0.97
0.96
0.9504
0.95
0.94
0.93
0.92
B0.91
.9089
0.90
I0.89
Silty Clay
Dry Density: 81.3 pcf
Initial Water Content: 15.1 %
Final Water Content: 24.7 %
H,O @ 400 PSF
0.88
0.87
0.86
0.8532
0.85
0.84
0.83
08341
0.82
0,8232
0.8136
0.8091
0.81
0.80
100
1000
10000
100000
Vertical Pressure (psf)
Sample Height (inches)](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F75d62a26-be63-41ba-a34f-383b9fb5d294%2F901eeb29-e8e7-4868-82e2-dfeeee0c552b%2F5g88kqc_processed.png&w=3840&q=75)
Transcribed Image Text:Please explain step by step. Thank you.
-> Find the preconsolidation pressure for curve below
-> Find Compression Index, (Cc) and Swell Index (Cs) for curve with initial void ratio assumed at = 0.8
-> Find total settlement
-> Can 50% Consolidation be achieved in 6 months if total surcharge applied is 2400 psf?
CONSOLIDATION TEST - ASTM D2435
Boring / Sample No.
B-10 / R-4
Depth:
7.5' - 9'
Date
03-18-19
1.00
0.9975
0.9950
0.99
- Natural
o Submerged
0.98
0.97
0.96
0.9504
0.95
0.94
0.93
0.92
B0.91
.9089
0.90
I0.89
Silty Clay
Dry Density: 81.3 pcf
Initial Water Content: 15.1 %
Final Water Content: 24.7 %
H,O @ 400 PSF
0.88
0.87
0.86
0.8532
0.85
0.84
0.83
08341
0.82
0,8232
0.8136
0.8091
0.81
0.80
100
1000
10000
100000
Vertical Pressure (psf)
Sample Height (inches)
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning