Good Homes Construction Company is about to begin the construction of a large new home. The company's President, Michael Dean, is currently planning the schedule for this project. Michael has identified the five major activities (labeled A, B, ..., E) that will need to be performed according to the following project network.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Please can you show me how this can be solved?

Problem 4
Good Homes Construction Company is about to begin the construction of a large new home. The company's
President, Michael Dean, is currently planning the schedule for this project. Michael has identified the five
major activities (labeled A, B, . . ., E) that will need to be performed according to the following project
network.
START
Activity
A
B
с
D
E
A
b)
Normal
Time
He also has gathered the following data about the normal point and crash point for each of these activities.
3 weeks
4 weeks
B
5 weeks
3 weeks
4 weeks
Crash
Time
2 weeks
3 weeks
2 weeks
1 week
2 weeks
Normal
Cost
D
$54,000
$62,000
$66,000
$40,000
$75,000
E
Crash
Cost
$60,000
$65,000
FINISH
$70,000
$43,000
$80,000
These costs reflect the company's direct costs for the material, equipment, and direct labor required to
perform the activities. In addition, the company incurs indirect project costs such as supervision and other
customary overhead costs, interest charges for capital tied up, and so forth. Michael estimates that these
indirect costs run $5,000 per week. He wants to minimize the overall cost of the project. Therefore, to save
some of these indirect costs, Michael concludes that he should shorten the project by doing some crashing to
the extent that the crashing cost for each additional week saved is less than $5,000.
a)
To prepare for analyzing the effect of crashing, find the earliest times, latest times, and slack for
each activity when they are done in the normal way. Also, identify the corresponding critical
path(s) and project duration.
Use the linear programming approach to determine which activities should be crashed and by
how much to minimize the overall cost of the project. How much money is saved by doing this
crashing?
Transcribed Image Text:Problem 4 Good Homes Construction Company is about to begin the construction of a large new home. The company's President, Michael Dean, is currently planning the schedule for this project. Michael has identified the five major activities (labeled A, B, . . ., E) that will need to be performed according to the following project network. START Activity A B с D E A b) Normal Time He also has gathered the following data about the normal point and crash point for each of these activities. 3 weeks 4 weeks B 5 weeks 3 weeks 4 weeks Crash Time 2 weeks 3 weeks 2 weeks 1 week 2 weeks Normal Cost D $54,000 $62,000 $66,000 $40,000 $75,000 E Crash Cost $60,000 $65,000 FINISH $70,000 $43,000 $80,000 These costs reflect the company's direct costs for the material, equipment, and direct labor required to perform the activities. In addition, the company incurs indirect project costs such as supervision and other customary overhead costs, interest charges for capital tied up, and so forth. Michael estimates that these indirect costs run $5,000 per week. He wants to minimize the overall cost of the project. Therefore, to save some of these indirect costs, Michael concludes that he should shorten the project by doing some crashing to the extent that the crashing cost for each additional week saved is less than $5,000. a) To prepare for analyzing the effect of crashing, find the earliest times, latest times, and slack for each activity when they are done in the normal way. Also, identify the corresponding critical path(s) and project duration. Use the linear programming approach to determine which activities should be crashed and by how much to minimize the overall cost of the project. How much money is saved by doing this crashing?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 5 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.