Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular time is limited to 150 units per month (Cost per Unit-$30) Overtime is limited to a maximum of 20 units per month (Cost per Unit -$45). Units purchased from the subcontractor (Cost per Unit - $54) cannot exceed 70 per month and the total purchases from the subcontractor over the 6 month period cannot be over 220 units. Backorders cannot exceed 60 units in any given month (Cost per Unit - $5) and must be no more than 10 in Period 6. Average Inventory Holding cost per Unit-$10. Forecasted Demand as well as Beginning and desired Ending Inventory are listed in the table below. Regular Output Overtime Output Month Subcontract Beginning Inventory Total Available for Sale Less Forecast Plus Backlog-Current Period Less Backlog-Previous Period Ending Inventory Average Inventory 20 190 1 170 2 270 3 180 4 160 190 10 Total Required i Find the Minimum Cost Production Plan by Creating a Spreadsheet in Excel. Use Solver to find the Minimum Cost Solution. Leave a copy of your Spreadsheet in the DropBox.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Required:
Find the Minimum Cost Production Plan by Creating a Spreadsheet in Excel. Use Solver to find the Minimum Cost
Solution. Leave a copy of your Spreadsheet in the DropBox.
Total Cost Month 1-
,5590)
Total Cost Month 2 =
,5470)
Total Cost Month 3 =
Total Cost Month 4 =
Total Cost Month 5=
,5420)
Total Cost Month 6-
A
AV
A
A
A
Total Cost All Periods
40180)
Answer Format: No Dollar ($) signs or commas- Answers should be whole numbers.
Hint: Range (5470
Hint: Range (5350
Hint: Range (5320
Hint: Range (38480
Transcribed Image Text:Required: Find the Minimum Cost Production Plan by Creating a Spreadsheet in Excel. Use Solver to find the Minimum Cost Solution. Leave a copy of your Spreadsheet in the DropBox. Total Cost Month 1- ,5590) Total Cost Month 2 = ,5470) Total Cost Month 3 = Total Cost Month 4 = Total Cost Month 5= ,5420) Total Cost Month 6- A AV A A A Total Cost All Periods 40180) Answer Format: No Dollar ($) signs or commas- Answers should be whole numbers. Hint: Range (5470 Hint: Range (5350 Hint: Range (5320 Hint: Range (38480
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time,
overtime, subcontract and backorders. Regular time is limited to 150 units per month (Cost per Unit-$30). Overtime
is limited to a maximum of 20 units per month (Cost per Unit-$45). Units purchased from the subcontractor (Cost per
Unit = $54) cannot exceed 70 per month and the total purchases from the subcontractor over the 6 month period
cannot be over 220 units. Backorders cannot exceed 60 units in any given month (Cost per Unit - $5) and must be no
more than 10 in Period 6. Average Inventory Holding cost per Unit = $10. Forecasted Demand as well as Beginning
and desired Ending Inventory are listed in the table below.
Regular Output
Overtime Output
Subcontract
Beginning Inventory
Month
Total Available for Sale
Less Forecast
Plus Backlog-Current Period
Less Backlog-Previous
Period
Ending Inventory
Average Inventory
20
190
1
170
2
3
270
180
4
160
190
10
6
Total
Required:
Find the Minimum Cost Production Plan by Creating a Spreadsheet in Excel. Use Solver to find the Minimum Cost
Solution. Leave a copy of your Spreadsheet in the DropBox.
Acti
Transcribed Image Text:Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular time is limited to 150 units per month (Cost per Unit-$30). Overtime is limited to a maximum of 20 units per month (Cost per Unit-$45). Units purchased from the subcontractor (Cost per Unit = $54) cannot exceed 70 per month and the total purchases from the subcontractor over the 6 month period cannot be over 220 units. Backorders cannot exceed 60 units in any given month (Cost per Unit - $5) and must be no more than 10 in Period 6. Average Inventory Holding cost per Unit = $10. Forecasted Demand as well as Beginning and desired Ending Inventory are listed in the table below. Regular Output Overtime Output Subcontract Beginning Inventory Month Total Available for Sale Less Forecast Plus Backlog-Current Period Less Backlog-Previous Period Ending Inventory Average Inventory 20 190 1 170 2 3 270 180 4 160 190 10 6 Total Required: Find the Minimum Cost Production Plan by Creating a Spreadsheet in Excel. Use Solver to find the Minimum Cost Solution. Leave a copy of your Spreadsheet in the DropBox. Acti
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.