Given the following schedule information and baseline budget, develop status reports for periods 1 – 4 and complete the summary graph (or a similar one). Report SV, CV, CPI, and PCIB. Write four status reports. One each for periods 1, 2, 3, and 4. Include an introduction in each status report which explains how far along the project is and what data is available. Use your own words, not those of the text or your classmates. Include the tabular form in each status report with the columns EV, PV, CV, and SV completed. Include a summary graph in each status report. Your choice is whether you choose to plot dollars or indices versus time period. Include an assessment of the status of the project in each status report. Again, use your own words. Include in each status report your forecast of the project at completion. Use extrapolated data to substantiate your claims. Schedule Information Baseline Budget ($000) Periods Activity Dur ES LF SL Pred PV 1 2 3 4 5 6 1 2 12 4 8 2 3 15 3 7 5 3 2 8 4 4 4 2 1 6 3 3 5 2 2,3 10 6 4 6 3 3 9 3 3 3 7 1 4,5,6 5 5 Total Planned Value (PV) by period 11 19 11 12 7 5 Cumulative PV by period 11 30 41 53 60 65 Status Report Ending Period 1 ($000) Activity % Complete EV AC PV CV SV 1 50% 6 2 40% 8 3 25% 3 4 0% 0 5 0% 0 6 0% 0 7 0% 0 Status Report Ending Period 2 ($000) Activity % Complete EV AC PV CV SV 1 100% 13 2 80% 14 3 75% 8 4 0% 0 5 0% 0 6 0% 0 7 0% 0 Status Report Ending Period 3 ($000) Activity % Complete EV AC PV CV SV 1 100% 13 2 80% 15 3 100% 10 4 50% 4 5 0% 0 6 33.3% 4 7 0% 0 Status Report Ending Period 4 ($000) Activity % Complete EV AC PV CV SV 1 100% 13 2 100% 18 3 100% 10 4 100% 8 5 30% 3 6 66.7% 8 7 0% 0
Given the following schedule information and baseline budget, develop status reports for periods 1 – 4 and complete the summary graph (or a similar one). Report SV, CV, CPI, and PCIB.
Write four status reports. One each for periods 1, 2, 3, and 4.
- Include an introduction in each status report which explains how far along the project is and what data is available. Use your own words, not those of the text or your classmates.
- Include the tabular form in each status report with the columns EV, PV, CV, and SV completed.
- Include a summary graph in each status report. Your choice is whether you choose to plot dollars or indices versus time period.
- Include an assessment of the status of the project in each status report. Again, use your own words.
- Include in each status report your forecast of the project at completion. Use extrapolated data to substantiate your claims.
Schedule Information |
Baseline Budget ($000) Periods |
|||||||||||
Activity |
Dur |
ES |
LF |
SL |
Pred |
PV |
1 |
2 |
3 |
4 |
5 |
6 |
1 |
2 |
|
|
|
|
12 |
4 |
8 |
|
|
|
|
2 |
3 |
|
|
|
|
15 |
3 |
7 |
5 |
|
|
|
3 |
2 |
|
|
|
|
8 |
4 |
4 |
|
|
|
|
4 |
2 |
|
|
|
1 |
6 |
|
|
3 |
3 |
|
|
5 |
2 |
|
|
|
2,3 |
10 |
|
|
|
6 |
4 |
|
6 |
3 |
|
|
|
3 |
9 |
|
|
3 |
3 |
3 |
|
7 |
1 |
|
|
|
4,5,6 |
5 |
|
|
|
|
|
5 |
Total Planned Value (PV) by period |
11 |
19 |
11 |
12 |
7 |
5 |
||||||
Cumulative PV by period |
11 |
30 |
41 |
53 |
60 |
65 |
Status Report Ending Period 1 ($000) |
||||||
Activity |
% Complete |
EV |
AC |
PV |
CV |
SV |
1 |
50% |
|
6 |
|
|
|
2 |
40% |
|
8 |
|
|
|
3 |
25% |
|
3 |
|
|
|
4 |
0% |
|
0 |
|
|
|
5 |
0% |
|
0 |
|
|
|
6 |
0% |
|
0 |
|
|
|
7 |
0% |
|
0 |
|
|
|
|
|
|
|
|
|
|
Status Report Ending Period 2 ($000) |
||||||
Activity |
% Complete |
EV |
AC |
PV |
CV |
SV |
1 |
100% |
|
13 |
|
|
|
2 |
80% |
|
14 |
|
|
|
3 |
75% |
|
8 |
|
|
|
4 |
0% |
|
0 |
|
|
|
5 |
0% |
|
0 |
|
|
|
6 |
0% |
|
0 |
|
|
|
7 |
0% |
|
0 |
|
|
|
|
|
|
|
|
|
|
Status Report Ending Period 3 ($000) |
||||||
Activity |
% Complete |
EV |
AC |
PV |
CV |
SV |
1 |
100% |
|
13 |
|
|
|
2 |
80% |
|
15 |
|
|
|
3 |
100% |
|
10 |
|
|
|
4 |
50% |
|
4 |
|
|
|
5 |
0% |
|
0 |
|
|
|
6 |
33.3% |
|
4 |
|
|
|
7 |
0% |
|
0 |
|
|
|
|
|
|
|
|
|
|
Status Report Ending Period 4 ($000) |
||||||
Activity |
% Complete |
EV |
AC |
PV |
CV |
SV |
1 |
100% |
|
13 |
|
|
|
2 |
100% |
|
18 |
|
|
|
3 |
100% |
|
10 |
|
|
|
4 |
100% |
|
8 |
|
|
|
5 |
30% |
|
3 |
|
|
|
6 |
66.7% |
|
8 |
|
|
|
7 |
0% |
|
0 |
|
|
|
|
|
|
|
|
|
|
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images