Given the following project management data: 02 05 04 06 08 R Activity B G H D How many paths are there in this network diagram? Time (Days) 6 5 7 5 7 2 6 7 A-B-E-G-H (6 +5+7+6+7)= 31 A-B-E-F-H (6 +5+7+2+7)= 27 A-C-E-G-H (6+7+7+ 6+ 7) = 33 A-C-E-F-H (6+7+7+2+7)=29 A-C-D-F-H (6+7+5+2+7)=27 H
Given the following project management data: 02 05 04 06 08 R Activity B G H D How many paths are there in this network diagram? Time (Days) 6 5 7 5 7 2 6 7 A-B-E-G-H (6 +5+7+6+7)= 31 A-B-E-F-H (6 +5+7+2+7)= 27 A-C-E-G-H (6+7+7+ 6+ 7) = 33 A-C-E-F-H (6+7+7+2+7)=29 A-C-D-F-H (6+7+5+2+7)=27 H
Related questions
Question

Transcribed Image Text:Given the following project management data:
02
05
04
В
00
Activity
A
B
С
D
Time (Days)
6
How many paths are there in this network diagram?
5
7
5
17
12
6
A-B-E-G-H (6+5+7+6+7)= 31
A-B-E-F-H (6 +5+7+2+7)= 27
A-C-E-G-H (6+7+7+6+7)= 33
A-C-E-F-H (6+7+7+2+ 7) = 29
A-C-D-F-H (6+7+5+2+7)= 27
H
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps