GIVEN D9N Dozer (Fig. 7.14) Move 2000 LCY Distance - 400 ft. (Fig. 7.14) Grade – 1% uphill (Table 7.2) Material - Loose stockpile (Table 7.2) • Operator Skills – Excellent (Table 7.2) Actual Time Working - 50 min/hr (Efficiency) • Operator Technique - slot dozing (Table 7.2) Visibility – N/A (Table 7.2) Material Weight- 2100 lb/CY (standard weight is 2300. Divide 2300 by material weight to get the factor) Transmission – Direct drive (Table 7.2) Dozer Blade - Straight blade D9N Book Efficiency (Fig. 7.14) X above factors Actual Efficiency Factors: grade x material weight x operator x type material x operator technique x visibility x efficiency x transmission x type blade

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
icon
Concept explainers
Question
Chapter 7
DOZER PRODUCTION EFFICIENCY
GIVEN
D9N Dozer (Fig. 7.14)
Move 2000 LCY
Distance - 400 ft. (Fig. 7.14)
Grade – 1% uphill (Table 7.2)
Material – Loose stockpile (Table 7.2)
• Operator Skills - Excellent (Table 7.2)
Actual Time Working - 50 min/hr (Efficiency)
Operator Technique - slot dozing (Table 7.2)
Visibility – N/A (Table 7.2)
Material Weight- 2100 lb/CY (standard weight is 2300. Divide 2300 by material
weight to get the factor)
Transmission - Direct drive (Table 7.2)
Dozer Blade - Straight blade
D9N Book Efficiency (Fig. 7.14) X above factors = Actual Efficiency
Factors: grade x material weight x operator x type material x operator technique x
visibility x efficiency x transmission x type blade
Efficiency x Factors = ActuaI Efficiency =
LCY/HR.
Transcribed Image Text:Chapter 7 DOZER PRODUCTION EFFICIENCY GIVEN D9N Dozer (Fig. 7.14) Move 2000 LCY Distance - 400 ft. (Fig. 7.14) Grade – 1% uphill (Table 7.2) Material – Loose stockpile (Table 7.2) • Operator Skills - Excellent (Table 7.2) Actual Time Working - 50 min/hr (Efficiency) Operator Technique - slot dozing (Table 7.2) Visibility – N/A (Table 7.2) Material Weight- 2100 lb/CY (standard weight is 2300. Divide 2300 by material weight to get the factor) Transmission - Direct drive (Table 7.2) Dozer Blade - Straight blade D9N Book Efficiency (Fig. 7.14) X above factors = Actual Efficiency Factors: grade x material weight x operator x type material x operator technique x visibility x efficiency x transmission x type blade Efficiency x Factors = ActuaI Efficiency = LCY/HR.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Pressure and stress
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning