ge 18-71 "P18.10 (LO 5, 6, 7) (Long-Term Contract Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 Contract costs incurred during the year $2,880,000 2021 2022 $2,880,000 $2,230,000 $2,190,000 3,520,000 2,190,000 -0- 3,200,000 3,500,000 Estimated costs to complete the contract at 12/31 Billings to Fabrik during the year 1,700,000 Instructions a. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) b. Using the completed-contract method, prepare schedules to compute the profit ocult of this contract for the years ended

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

Hello please can you explain the step on the exercise were do the number come from thanks

Question
8
Page 18-71
W
*P18.10 (LO 5, 6, 7) (Long-Term Contract with Interim Loss) On March 1, 2020,
Pechstein Construction Company contracted to construct a factory building for
Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was
completed by October 31, 2022. The annual contract costs incurred, estimated
costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021,
and 2022 are given below.
2020
2021
2022
Contract costs incurred during the year $2,880,000 $2,230,000 $2,190,000
Estimated costs to complete the
3,520,000
2,190,000
-0-
contract at 12/31
Billings to Fabrik during the year
3,200,000
Dr your resume
3,500,000
Instructions
a. Using the percentage-of-completion method, prepare schedules to compute
the profit or loss to be recognized as a result of this contract for the years
ended December 31, 2020, 2021, and 2022. (Ignore income taxes.)
b. Using the completed-contract method, prepare schedules to compute the profit
or loss to be recognized as a result of this contract for the years ended
December 31, 2020, 2021, and 2022. (Ignore incomes taxes.)
Korpul Wind
1,700,000
Resume 12023
(1) P
많
Try free
Po
Ar
to
2
Transcribed Image Text:Question 8 Page 18-71 W *P18.10 (LO 5, 6, 7) (Long-Term Contract with Interim Loss) On March 1, 2020, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $2,880,000 $2,230,000 $2,190,000 Estimated costs to complete the 3,520,000 2,190,000 -0- contract at 12/31 Billings to Fabrik during the year 3,200,000 Dr your resume 3,500,000 Instructions a. Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) b. Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore incomes taxes.) Korpul Wind 1,700,000 Resume 12023 (1) P 많 Try free Po Ar to 2
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education