Fuji Software Inc. has the following mutually exclusive projects. Project Project Year 0 4 -$32,000-$35,000 18,000 14,500 13,000 4,100 14,100 10,000 a-1. Calculate the payback period for each project. (Do not round Intermediate calculations. Round the answers to 3 decimal places) Project A Project s Payback period 1.966 2.207 years years e-2. Which, if either, of these projects should be chosen? Project A Project B

Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
icon
Related questions
icon
Concept explainers
Topic Video
Question

.

Fuji Software Inc. has the following mutually exclusive projects.
Year Project
-$32,000
0
1
3
Project A
Project s
18,000
14,500
4,100
a-1. Calculate the payback period for each project. (Do not round Intermediate calculations. Round the answers to 3 decimal
places.)
Project
-$35,000
19,000
Project A
Project
13,000
14,500
Payback period
a-2. Which, if either, of these projects should be chosen?
Project A
Project B
Both projects
ⒸNeither project
1.966 years
2.207
years
ⒸProject A
D-1 What is the NPV for each project if the appropriate discount rate is 15 percent? (Do not round Intermediate calculations. Negative
amounts should be indicated by a minus sign. Round the answers to 2 decimal places. Omit $ sign in your response.)
NPV
$ -2,570.97
1,840.43
D-2. Which, if either of these projects should be chosen if the appropriate discount rate is 15 percent?
Project BO
Both projects
Neither project
Transcribed Image Text:Fuji Software Inc. has the following mutually exclusive projects. Year Project -$32,000 0 1 3 Project A Project s 18,000 14,500 4,100 a-1. Calculate the payback period for each project. (Do not round Intermediate calculations. Round the answers to 3 decimal places.) Project -$35,000 19,000 Project A Project 13,000 14,500 Payback period a-2. Which, if either, of these projects should be chosen? Project A Project B Both projects ⒸNeither project 1.966 years 2.207 years ⒸProject A D-1 What is the NPV for each project if the appropriate discount rate is 15 percent? (Do not round Intermediate calculations. Negative amounts should be indicated by a minus sign. Round the answers to 2 decimal places. Omit $ sign in your response.) NPV $ -2,570.97 1,840.43 D-2. Which, if either of these projects should be chosen if the appropriate discount rate is 15 percent? Project BO Both projects Neither project
Expert Solution
steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Essentials Of Investments
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
FUNDAMENTALS OF CORPORATE FINANCE
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:
9781260013962
Author:
BREALEY
Publisher:
RENT MCG
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
Foundations Of Finance
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education