Foundation engineers are often challenged by the existence of soft compress- ible soils at the construction site. Figure shows a soil profile with a silty sand (y = 17 kN/m³; Ysat = 19.2 kN/m³) underlain by high plasticity clay (Ysal = 18.8 kN/m³) and a peat layer (Ysat = 15 kN/m³), followed by dense sand. To expedite consolidation and minimize future settlement, an additional 1.75-m thick fill material, compacted to a unit weight of 20.1 kN/m³, will be placed on top of the silty sand layer. The plan area of the fill is 8 m x 8 m. The fill load will be left in place for 18 months, after which construction will begin with the fill becoming part of the permanent foundation. Undisturbed samples col- lected from the clay and organic layers had the following properties: Layer's Clay Peat Ce 0.31 7.2 Ca 0.048 0.273 a. Estimate the total consolidation settlement under the action of the fill load. Consider both the clay and peat layers to be normally consolidated. b. Estimate the time for 99% primary consolidation in each layer. Are the layers singly or doubly drained? Explain. T 1.5 m. Silty sand 4 1.5 m. C. Estimate the secondary compression in each layer up to end of 18 months. d. What will be the total settlement after 18 months? e. What is the remaining excess pore water pressure at point A two months after the application of the fill load? 4 m Clay c, (cm²/sec) 0.006 0.029 1.8 m Peat- ↓ Co 1.08 6.4 Fill load (kN/m²) Dense sand 3.2 m ↓↓↓ A Piezometer GWT
Foundation engineers are often challenged by the existence of soft compress- ible soils at the construction site. Figure shows a soil profile with a silty sand (y = 17 kN/m³; Ysat = 19.2 kN/m³) underlain by high plasticity clay (Ysal = 18.8 kN/m³) and a peat layer (Ysat = 15 kN/m³), followed by dense sand. To expedite consolidation and minimize future settlement, an additional 1.75-m thick fill material, compacted to a unit weight of 20.1 kN/m³, will be placed on top of the silty sand layer. The plan area of the fill is 8 m x 8 m. The fill load will be left in place for 18 months, after which construction will begin with the fill becoming part of the permanent foundation. Undisturbed samples col- lected from the clay and organic layers had the following properties: Layer's Clay Peat Ce 0.31 7.2 Ca 0.048 0.273 a. Estimate the total consolidation settlement under the action of the fill load. Consider both the clay and peat layers to be normally consolidated. b. Estimate the time for 99% primary consolidation in each layer. Are the layers singly or doubly drained? Explain. T 1.5 m. Silty sand 4 1.5 m. C. Estimate the secondary compression in each layer up to end of 18 months. d. What will be the total settlement after 18 months? e. What is the remaining excess pore water pressure at point A two months after the application of the fill load? 4 m Clay c, (cm²/sec) 0.006 0.029 1.8 m Peat- ↓ Co 1.08 6.4 Fill load (kN/m²) Dense sand 3.2 m ↓↓↓ A Piezometer GWT
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
100%
Hand written work please

Transcribed Image Text:Foundation engineers are often challenged by the existence of soft compress-
ible soils at the construction site. Figure shows a soil profile with a silty
=
sand (y = 17 kN/m³; Ysat = 19.2 kN/m³) underlain by high plasticity clay
(Ysat 18.8 kN/m³) and a peat layer (Ysat = 15 kN/m³), followed by dense sand.
To expedite consolidation and minimize future settlement, an additional 1.75-m
thick fill material, compacted to a unit weight of 20.1 kN/m³, will be placed on
top of the silty sand layer. The plan area of the fill is 8 m x 8 m. The fill load
will be left in place for 18 months, after which construction will begin with the
fill becoming part of the permanent foundation. Undisturbed samples col-
lected from the clay and organic layers had the following properties:
Layer
Clay
Peat
Ce
0.31
7.2
Ca
0.048
0.273
a. Estimate the total consolidation settlement under the action of the fill
load. Consider both the clay and peat layers to be normally consolidated.
b. Estimate the time for 99% primary consolidation in each layer. Are the
layers singly or doubly drained? Explain.
T
1.5 m. Silty sand
1.5 m.
C. Estimate the secondary compression in each layer up to end of 18 months.
d. What will be the total settlement after 18 months?
e. What is the remaining excess pore water pressure at point A two months
after the application of the fill load?
4 m Clay
c, (cm²/sec)
0.006
0.029
1.8 m Peat-
↓
Co
1.08
6.4
Fill load (kN/m²)
Dense sand
3.2 m
↓ ↓ ↓
A Piezometer
GWT
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 6 steps with 4 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning