For the given information related to "inputs," the values for deviation and total are: The deviation in period 2 = units (enter your response as an integer, including a minus sign if necessary). The deviation in period 4 = units (enter your response as an integer, including a minus sign if necessary). The total for "planned inputs" = units (enter your response as an integer, including a minus sign if necessary). The total for "actual inputs" = units (enter your response as an integer, including a minus sign if necessary). The total deviation for "inputs" = units (enter your response as an integer, including a minus sign if necessary). For the given information related to "outputs," the values for deviation and total are: The deviation in period 1 = units (enter your response as an integer, including a minus sign if necessary). The deviation in period 3 = units (enter your response as an integer, including a minus sign if necessary). The total for "planned outputs" = units (enter your response as an integer, including a minus sign if necessary). units (enter your response as an integer, including a minus sign if necessary). The total for "actual outputs" = The total deviation for "outputs" = units (enter your response as an integer, including a minus sign if necessary). Fill in the cumulative values for the backlog in each of the periods (given an initial backlog of 20): Period 1 2 3 4 Total Initial backlog: 20

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Lifang Wu owns an automated machine shop that makes precision auto parts. He has just compiled an input-output report for the grinding work center.
Period
1
3
4
Total
Planned input
70
70
85
85
Actual input
75
75
75
75
Deviation
Planned output
Actual output
75
75
75
75
85
85
80
80
Deviation
Initial backlog: 20
For the given information related to "inputs," the values for deviation and total are:
The deviation in period 2 =
units (enter your response as an integer, including a minus sign if necessary).
The deviation in period 4 =
units (enter your response as an integer, including a minus sign if necessary).
The total for "planned inputs" =
units (enter your response as an integer, including a minus sign if necessary).
The total for "actual inputs" =
units (enter your response as an integer, including a minus sign if necessary).
The total deviation for "inputs" = units (enter your response as an integer, including a minus sign if necessary).
"3D
For the given information related to "outputs," the values for deviation and total are:
The deviation in period 1 =
units (enter your response as an integer, including a minus sign if necessary).
The deviation in period 3 =
units (enter your response as an integer, including a minus sign if necessary).
The total for "planned outputs" =
units (enter your response as an integer, including a minus sign if necessary).
The total for "actual outputs" =
units (enter your response as an integer, including a minus sign if necessary).
The total deviation for "outputs" =
units (enter your response as an integer, including a minus sign if necessary).
Fill in the cumulative values for the backlog in each of the periods (given an initial backlog of 20):
Period
1
2
3
4
Total
Initial backlog: 20
Transcribed Image Text:Lifang Wu owns an automated machine shop that makes precision auto parts. He has just compiled an input-output report for the grinding work center. Period 1 3 4 Total Planned input 70 70 85 85 Actual input 75 75 75 75 Deviation Planned output Actual output 75 75 75 75 85 85 80 80 Deviation Initial backlog: 20 For the given information related to "inputs," the values for deviation and total are: The deviation in period 2 = units (enter your response as an integer, including a minus sign if necessary). The deviation in period 4 = units (enter your response as an integer, including a minus sign if necessary). The total for "planned inputs" = units (enter your response as an integer, including a minus sign if necessary). The total for "actual inputs" = units (enter your response as an integer, including a minus sign if necessary). The total deviation for "inputs" = units (enter your response as an integer, including a minus sign if necessary). "3D For the given information related to "outputs," the values for deviation and total are: The deviation in period 1 = units (enter your response as an integer, including a minus sign if necessary). The deviation in period 3 = units (enter your response as an integer, including a minus sign if necessary). The total for "planned outputs" = units (enter your response as an integer, including a minus sign if necessary). The total for "actual outputs" = units (enter your response as an integer, including a minus sign if necessary). The total deviation for "outputs" = units (enter your response as an integer, including a minus sign if necessary). Fill in the cumulative values for the backlog in each of the periods (given an initial backlog of 20): Period 1 2 3 4 Total Initial backlog: 20
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.