For question use either UnBBayes or Netica to build your models. Note that you must provide your modeling assumptions and a running model (i.e. not just a screenshot). Like Noisy-OR BN models.SnowLair, Inc., has issued a contract to design an upgrade to an existing firewall system. Based on the results of a preliminary design review, the program manager believes that a critical driver of success of the upgrade is the impact to the system that a new, untested technology that the company is proposing to use would have. Based on engineering analyses, the program manager believes: • There is a 75% chance that the new technology will be deployed successfully in the new system without impacting cost, schedule, and performance, a 20% chance of a moderate impact, and a 5% chance of a severe impact. If there is no impact, the program manager forecasts a 75% chance of a cost overrun smaller than $10K, and a 25% chance of an overrun greater than $10K. A moderate impact means 60% chance of a cost overrun smaller than $10K, a 40% chance of overrun greater than $10K. A severe impact means a 20% chance of no overrun, a 80% chance of greater than $10K overrun. • If there is no impact, the program manager forecasts an 80% chance of on-time delivery and a 20% chance of a delay. A moderate impact means 50% chance of on- time delivery and a 50% chance of a delay. A severe impact means 5% chance of on- time delivery and a 95% chance of a delay. • If there is no impact, the program manager forecasts a 90% chance of an acceptable performance and a 10% chance of unacceptable performance. A moderate impact means 70% chance of an acceptable performance and a 30% chance of unacceptable performance. A severe impact means a 10% chance of an acceptable performance and a 90% chance of unacceptable performance. a. Construct a Bayesian network to model this problem. b. The program manager also wants to estimate the fairness of the procurement process. For this, he will only consider the procurement a failure if a cost overrun greater than $10K, a delayed delivery, and an unacceptable performance all occur *at the same time", while all other combinations of those factors would be considered a fair project. He estimates that Cost Overrun impacts Fairness of a project at 80%, Delivery Time has a 40% impact, while Performance would have a 60% impact. He also believes that the mechanisms by which Cost Overrun, Delivery Time, and Performance affect Fairness are mutually independent. Calculate what is the posterior probability of a fair procurement given that a moderate impact would happen

Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
icon
Related questions
Question

For question use either UnBBayes or Netica to build your models. Note that you
must provide your modeling assumptions and a running model (i.e. not just a screenshot). Like Noisy-OR BN models.SnowLair, Inc., has issued a contract to design an upgrade to an existing firewall system. Based on the results of a preliminary design review, the program manager believes that a critical driver of success of the upgrade is the impact to the system that a new, untested technology that the company is proposing to use would have. Based on engineering analyses, the program manager believes:

• There is a 75% chance that the new technology will be deployed successfully in the new system without impacting cost, schedule, and performance, a 20% chance of a moderate impact, and a 5% chance of a severe impact.

If there is no impact, the program manager forecasts a 75% chance of a cost overrun smaller than $10K, and a 25% chance of an overrun greater than $10K. A moderate impact means 60% chance of a cost overrun smaller than $10K, a 40% chance of overrun greater than $10K. A severe impact means a 20% chance of no overrun, a 80% chance of greater than $10K overrun.

• If there is no impact, the program manager forecasts an 80% chance of on-time delivery and a 20% chance of a delay. A moderate impact means 50% chance of on- time delivery and a 50% chance of a delay. A severe impact means 5% chance of on- time delivery and a 95% chance of a delay.

• If there is no impact, the program manager forecasts a 90% chance of an acceptable performance and a 10% chance of unacceptable performance. A moderate impact means 70% chance of an acceptable performance and a 30% chance of unacceptable performance. A severe impact means a 10% chance of an acceptable performance and a 90% chance of unacceptable performance.

a. Construct a Bayesian network to model this problem.

b. The program manager also wants to estimate the fairness of the procurement process. For this, he will only consider the procurement a failure if a cost overrun greater than $10K, a delayed delivery, and an unacceptable performance all occur *at the same time", while all other combinations of those factors would be considered a fair project. He estimates that Cost Overrun impacts Fairness of a project at 80%, Delivery Time has a 40% impact, while Performance would have a 60% impact. He also believes that the mechanisms by which Cost Overrun, Delivery Time, and Performance affect Fairness are mutually independent. Calculate what is the posterior probability of a fair procurement given that a moderate impact would happen. 

Expert Solution
steps

Step by step

Solved in 4 steps with 1 images

Blurred answer
Knowledge Booster
Requirements of secure softwares
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Database System Concepts
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
C How to Program (8th Edition)
C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON
Database Systems: Design, Implementation, & Manag…
Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning
Programmable Logic Controllers
Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education