Ezra Construction Co. ("ECC") started business in 2020 and accepted its first contract to construct a building for $2.3 million, starting March 1, 2020. The planned completion date is December 2022. ECC uses the percentage-of-completion method of accounting for long-term contracts. Percentage-of-completion is measured based on total costs incurred compared to total estimated construction costs. ECC uses IFRS and its year-end is December 31. Certain data related to the contract are summarized below: Dec. 31, 2020 Dec. 31, 2021 370,000 Costs incurred during the year Est'd remaining costs to complete Progress billings to date Cash collections during the year 330,000 1,170,000 410,000 375,000 900,000 967,000 485,000 REQUIRED A. Prepare all required journal entries for 2020 and 2021. B. What should be the balance of Accounts Receivable as of December 31, 2021? C. What should be the balance of Construction-in-Progress (CIP) Inventory as of December 31, 2021? D. Ignore your answers to parts (A), (B), and (C) above. If the "Estimated remaining costs to complete" at December 31, 2020 was $2,126,000, instead of $1,170,000. How much should be the Income (Loss) before income taxes for the year 2020? Show your work clearly. E. Ignore your answers to parts (A), (B), (C), and (D) above. If the "Estimated remaining costs to complete" at December 31, 2021 was $1,870,000, instead of $900,000. How much should be the Income (Loss) before income taxes for the year 2021? Show your work clearly

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Ezra Construction Co. ("ECC") started business in 2020 and accepted its first contract to construct a
building for $2.3 million, starting March 1, 2020. The planned completion date is December 2022. ECC
uses the percentage-of-completion method of accounting for long-term contracts. Percentage-of-completion
is measured based on total costs incurred compared to total estimated construction costs. ECC uses IFRS
and its year-end is December 31. Certain data related to the contract are summarized below:
Dec. 31, 2020
Dec. 31, 2021
Costs incurred during the year
Est'd remaining costs to complete
Progress billings to date
Cash collections during the year
330,000
370,000
900,000
967,000
485,000
1,170,000
410,000
375,000
REQUIRED
A. Prepare all required journal entries for 2020 and 2021.
B. What should be the balance of Accounts Receivable as of December 31, 2021?
C. What should be the balance of Construction-in-Progress (CIP) Inventory as of December 31,
2021?
D. Ignore your answers to parts (A), (B), and (C) above. If the "Estimated remaining costs to
complete" at December 31, 2020 was $2,126,000, instead of $1,170,000. How much should be the
Income (Loss) before income taxes for the year 2020? Show your work clearly.
E. Ignore your answers to parts (A), (B), (C), and (D) above. If the "Estimated remaining costs to
complete" at December 31, 2021 was $1,870,000, instead of $900,000. How much should be the
Income (Loss) before income taxes for the year 2021? Show your work clearly
Transcribed Image Text:Ezra Construction Co. ("ECC") started business in 2020 and accepted its first contract to construct a building for $2.3 million, starting March 1, 2020. The planned completion date is December 2022. ECC uses the percentage-of-completion method of accounting for long-term contracts. Percentage-of-completion is measured based on total costs incurred compared to total estimated construction costs. ECC uses IFRS and its year-end is December 31. Certain data related to the contract are summarized below: Dec. 31, 2020 Dec. 31, 2021 Costs incurred during the year Est'd remaining costs to complete Progress billings to date Cash collections during the year 330,000 370,000 900,000 967,000 485,000 1,170,000 410,000 375,000 REQUIRED A. Prepare all required journal entries for 2020 and 2021. B. What should be the balance of Accounts Receivable as of December 31, 2021? C. What should be the balance of Construction-in-Progress (CIP) Inventory as of December 31, 2021? D. Ignore your answers to parts (A), (B), and (C) above. If the "Estimated remaining costs to complete" at December 31, 2020 was $2,126,000, instead of $1,170,000. How much should be the Income (Loss) before income taxes for the year 2020? Show your work clearly. E. Ignore your answers to parts (A), (B), (C), and (D) above. If the "Estimated remaining costs to complete" at December 31, 2021 was $1,870,000, instead of $900,000. How much should be the Income (Loss) before income taxes for the year 2021? Show your work clearly
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Consolidations
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education