Exercise 15-17 (Algo) Overhead rate; costs assigned to jobs LO P3 Shire Company's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $826,000 of overhead costs and $590,000 of direct labor cost for the period. During March, Shire began and completed Job 56. 1. What is the predetermined overhead rate for this period? 2. Use the Information on the following job cost sheet to determine the total cost of Job 56. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Use the information on the following job cost sheet to determine the total cost of Job 56. Note: Round your answers to the nearest dollar amount. Customer's Name: Keiser Company Job Description: 3 customized systems Direct Materials Date March 08 March 11 March 18 Requisition Number M-129 M-142 M-167 Cost JOB COST SHEET Direct Labor Time-Ticket Number S 4.000 T-300 6,600 T-432 3.300 T-456 Required 1 S Cost Job Number: 56 1,350 1,330 Overhead Applied 680 S 952 1,800 1.802 Required 2 > Total Cost

College Accounting, Chapters 1-27
23rd Edition
ISBN:9781337794756
Author:HEINTZ, James A.
Publisher:HEINTZ, James A.
Chapter26: Manufacturing Accounting: The Job Order Cost System
Section: Chapter Questions
Problem 5SEB: PREDETERMINED FACTORY OVERHEAD RATE Marston Enterprises calculates a predetermined factory overhead...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Exercise 15-17 (Algo) Overhead rate; costs assigned to jobs LO P3
Shire Company's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $826,00
of overhead costs and $590,000 of direct labor cost for the period. During March, Shire began and completed Job 56.
1. What is the predetermined overhead rate for this period?
2. Use the Information on the following job cost sheet to determine the total cost of Job 56.
Complete this question by entering your answers in the tabs below.
Required 1 Required 2
What is the predetermined overhead rate for this period?
Overhead Rate
Numerator:
1
1
Denominator:
< Required 1
Overhead Rate
Overhead rate
Required 2 >
Transcribed Image Text:Exercise 15-17 (Algo) Overhead rate; costs assigned to jobs LO P3 Shire Company's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $826,00 of overhead costs and $590,000 of direct labor cost for the period. During March, Shire began and completed Job 56. 1. What is the predetermined overhead rate for this period? 2. Use the Information on the following job cost sheet to determine the total cost of Job 56. Complete this question by entering your answers in the tabs below. Required 1 Required 2 What is the predetermined overhead rate for this period? Overhead Rate Numerator: 1 1 Denominator: < Required 1 Overhead Rate Overhead rate Required 2 >
Exercise 15-17 (Algo) Overhead rate; costs assigned to jobs LO P3
Shire Company's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $826,000
of overhead costs and $590,000 of direct labor cost for the period. During March, Shire began and completed Job 56.
1. What is the predetermined overhead rate for this period?
2. Use the Information on the following job cost sheet to determine the total cost of Job 56.
Complete this question by entering your answers in the tabs below.
Required 1 Required 2
Use the information on the following job cost sheet to determine the total cost of Job 56.
Note: Round your answers to the nearest dollar amount.
Customer's Name: Keiser Company
Job Description: 3 customized systems
Direct Materials
Date
March 08
March 11
March 18
Requisition
Number
M-129
M-142
M-107
Cost
JOB COST SHEET
Direct Labor
Time-Ticket
Number
S 4.000 T-300
6,600 T-432
3.300 T-456
< Required 1
S
Cost
Job Number: 56
1,350
1,330
Overhead
Applied
680 S
952
1,800
1.862
Required 2 >
Total Cost
Transcribed Image Text:Exercise 15-17 (Algo) Overhead rate; costs assigned to jobs LO P3 Shire Company's predetermined overhead rate is based on direct labor cost. Management estimates the company will incur $826,000 of overhead costs and $590,000 of direct labor cost for the period. During March, Shire began and completed Job 56. 1. What is the predetermined overhead rate for this period? 2. Use the Information on the following job cost sheet to determine the total cost of Job 56. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Use the information on the following job cost sheet to determine the total cost of Job 56. Note: Round your answers to the nearest dollar amount. Customer's Name: Keiser Company Job Description: 3 customized systems Direct Materials Date March 08 March 11 March 18 Requisition Number M-129 M-142 M-107 Cost JOB COST SHEET Direct Labor Time-Ticket Number S 4.000 T-300 6,600 T-432 3.300 T-456 < Required 1 S Cost Job Number: 56 1,350 1,330 Overhead Applied 680 S 952 1,800 1.862 Required 2 > Total Cost
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
College Accounting, Chapters 1-27
College Accounting, Chapters 1-27
Accounting
ISBN:
9781337794756
Author:
HEINTZ, James A.
Publisher:
Cengage Learning,
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
College Accounting, Chapters 1-27 (New in Account…
College Accounting, Chapters 1-27 (New in Account…
Accounting
ISBN:
9781305666160
Author:
James A. Heintz, Robert W. Parry
Publisher:
Cengage Learning