Earned Value Management (EVM) is a method or an approach in measuring the project performance throughout the project at any point of time that integrates the variances of cost and schedule in assisting organizations to decide either to continue or terminate the project. 1. Within 200 days, the equipment supplier has agreed to supply 100 units of spare equipment at the price of RM500 per unit. However, 50 days later, the supplier can only supply 21 units with an actual total cost of RM11,400. a. Indicate either the supply is ahead or behind the schedule (in days). b. Indicate either the supply is under or exceed the budget (in amount). c. Indicate the cost performance of the supply (in percentage) d. Indicate the performance of the supply in term of schedule (in percentage)

Excel Applications for Accounting Principles
4th Edition
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Gaylord N. Smith
ChapterMB: Model-building Problems
Section: Chapter Questions
Problem 18M
icon
Related questions
Question

PROJECT MANAGEMENT

Earned Value Management (EVM) is a method or an approach in measuring the project performance
throughout the project at any point of time that integrates the variances of cost and schedule in
assisting organizations to decide either to continue or terminate the project.
1. Within 200 days, the equipment supplier has agreed to supply 100 units of spare equipment at the
price of RM500 per unit. However, 50 days later, the supplier can only supply 21 units with an
actual total cost of RM11,400.
a. Indicate either the supply is ahead or behind the schedule (in days).
b. Indicate either the supply is under or exceed the budget (in amount).
c. Indicate the cost performance of the supply (in percentage)
d. Indicate the performance of the supply in term of schedule (in percentage)
Transcribed Image Text:Earned Value Management (EVM) is a method or an approach in measuring the project performance throughout the project at any point of time that integrates the variances of cost and schedule in assisting organizations to decide either to continue or terminate the project. 1. Within 200 days, the equipment supplier has agreed to supply 100 units of spare equipment at the price of RM500 per unit. However, 50 days later, the supplier can only supply 21 units with an actual total cost of RM11,400. a. Indicate either the supply is ahead or behind the schedule (in days). b. Indicate either the supply is under or exceed the budget (in amount). c. Indicate the cost performance of the supply (in percentage) d. Indicate the performance of the supply in term of schedule (in percentage)
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Enterprise resource planning (ERP)
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Excel Applications for Accounting Principles
Excel Applications for Accounting Principles
Accounting
ISBN:
9781111581565
Author:
Gaylord N. Smith
Publisher:
Cengage Learning
Essentials of Business Analytics (MindTap Course …
Essentials of Business Analytics (MindTap Course …
Statistics
ISBN:
9781305627734
Author:
Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:
Cengage Learning