Earned Value Management (EVM) is a method or an approach in measuring the project performance throughout the project at any point of time that integrates the variances of cost and schedule in assisting organizations to decide either to continue or terminate the project. 1. Within 200 days, the equipment supplier has agreed to supply 100 units of spare equipment at the price of RM500 per unit. However, 50 days later, the supplier can only supply 21 units with an actual total cost of RM11,400. a. Indicate either the supply is ahead or behind the schedule (in days). b. Indicate either the supply is under or exceed the budget (in amount). c. Indicate the cost performance of the supply (in percentage) d. Indicate the performance of the supply in term of schedule (in percentage)

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

PROJECT MANAGEMENT

Earned Value Management (EVM) is a method or an approach in measuring the project performance
throughout the project at any point of time that integrates the variances of cost and schedule in
assisting organizations to decide either to continue or terminate the project.
1. Within 200 days, the equipment supplier has agreed to supply 100 units of spare equipment at the
price of RM500 per unit. However, 50 days later, the supplier can only supply 21 units with an
actual total cost of RM11,400.
a. Indicate either the supply is ahead or behind the schedule (in days).
b. Indicate either the supply is under or exceed the budget (in amount).
c. Indicate the cost performance of the supply (in percentage)
d. Indicate the performance of the supply in term of schedule (in percentage)
Transcribed Image Text:Earned Value Management (EVM) is a method or an approach in measuring the project performance throughout the project at any point of time that integrates the variances of cost and schedule in assisting organizations to decide either to continue or terminate the project. 1. Within 200 days, the equipment supplier has agreed to supply 100 units of spare equipment at the price of RM500 per unit. However, 50 days later, the supplier can only supply 21 units with an actual total cost of RM11,400. a. Indicate either the supply is ahead or behind the schedule (in days). b. Indicate either the supply is under or exceed the budget (in amount). c. Indicate the cost performance of the supply (in percentage) d. Indicate the performance of the supply in term of schedule (in percentage)
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Enterprise resource planning (ERP)
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education