Draw the graph and the schematic of the rectangles with all the network calculations for the project whose details are shown in the table below, then answer the questions below Time (week) Activity Dependency Resource a m b 2 4 6. 4 B 3 6. 1 C 1 2 3 2 A 2 8 3 E А, В, С 2 4 6. 1 F A, B, C Е, F 1 3 G 2 8 3
Draw the graph and the schematic of the rectangles with all the network calculations for the project whose details are shown in the table below, then answer the questions below Time (week) Activity Dependency Resource a m b 2 4 6. 4 B 3 6. 1 C 1 2 3 2 A 2 8 3 E А, В, С 2 4 6. 1 F A, B, C Е, F 1 3 G 2 8 3
Advanced Engineering Mathematics
10th Edition
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Erwin Kreyszig
Chapter2: Second-order Linear Odes
Section: Chapter Questions
Problem 1RQ
Related questions
Concept explainers
Contingency Table
A contingency table can be defined as the visual representation of the relationship between two or more categorical variables that can be evaluated and registered. It is a categorical version of the scatterplot, which is used to investigate the linear relationship between two variables. A contingency table is indeed a type of frequency distribution table that displays two variables at the same time.
Binomial Distribution
Binomial is an algebraic expression of the sum or the difference of two terms. Before knowing about binomial distribution, we must know about the binomial theorem.
Topic Video
Question
I need the answer quickly
![Draw the graph and the schematic of the
rectangles with all the network
calculations for the project whose details
are shown in the table below, then
answer the questions below
Time (week)
Activity
Dependency
Resource
a
m
b
A
4
4
B
1
1
2
3
A
8
E
А, В, С
A, B, C
E, F
4
6.
1
F
1
2
2
8
3
Find critical events
Find the value of the variance for the critical path in the
project
Find the value of the standard deviation for the critical
path in the project
Find the probability of completing the project in a time less
than or equal to the critical path time plus one week
Find the probability of completing the project in a time
greater than the critical path time plus one week
Find the closest value to the pessimistic time to complete
the project
What is the time to complete the completion of the project
that achieves a probability of 90%](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F3008c1c0-2b03-4eca-9ae3-5bdad058e1f4%2Ff82cce3b-6a02-4aa4-8e93-11ba6c4824f8%2Fdl95qmn_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Draw the graph and the schematic of the
rectangles with all the network
calculations for the project whose details
are shown in the table below, then
answer the questions below
Time (week)
Activity
Dependency
Resource
a
m
b
A
4
4
B
1
1
2
3
A
8
E
А, В, С
A, B, C
E, F
4
6.
1
F
1
2
2
8
3
Find critical events
Find the value of the variance for the critical path in the
project
Find the value of the standard deviation for the critical
path in the project
Find the probability of completing the project in a time less
than or equal to the critical path time plus one week
Find the probability of completing the project in a time
greater than the critical path time plus one week
Find the closest value to the pessimistic time to complete
the project
What is the time to complete the completion of the project
that achieves a probability of 90%
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 4 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, advanced-math and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Advanced Engineering Mathematics](https://www.bartleby.com/isbn_cover_images/9780470458365/9780470458365_smallCoverImage.gif)
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
![Numerical Methods for Engineers](https://www.bartleby.com/isbn_cover_images/9780073397924/9780073397924_smallCoverImage.gif)
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
![Introductory Mathematics for Engineering Applicat…](https://www.bartleby.com/isbn_cover_images/9781118141809/9781118141809_smallCoverImage.gif)
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
![Advanced Engineering Mathematics](https://www.bartleby.com/isbn_cover_images/9780470458365/9780470458365_smallCoverImage.gif)
Advanced Engineering Mathematics
Advanced Math
ISBN:
9780470458365
Author:
Erwin Kreyszig
Publisher:
Wiley, John & Sons, Incorporated
![Numerical Methods for Engineers](https://www.bartleby.com/isbn_cover_images/9780073397924/9780073397924_smallCoverImage.gif)
Numerical Methods for Engineers
Advanced Math
ISBN:
9780073397924
Author:
Steven C. Chapra Dr., Raymond P. Canale
Publisher:
McGraw-Hill Education
![Introductory Mathematics for Engineering Applicat…](https://www.bartleby.com/isbn_cover_images/9781118141809/9781118141809_smallCoverImage.gif)
Introductory Mathematics for Engineering Applicat…
Advanced Math
ISBN:
9781118141809
Author:
Nathan Klingbeil
Publisher:
WILEY
![Mathematics For Machine Technology](https://www.bartleby.com/isbn_cover_images/9781337798310/9781337798310_smallCoverImage.jpg)
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,
![Basic Technical Mathematics](https://www.bartleby.com/isbn_cover_images/9780134437705/9780134437705_smallCoverImage.gif)
![Topology](https://www.bartleby.com/isbn_cover_images/9780134689517/9780134689517_smallCoverImage.gif)