Down Under Boomerang, Inc., is considering a new 3-year expansion project that requires an initial fixed asset investment of $2.3 million. The fixed asset will be depreciated straight-line to zero over its 3-year tax life. The project is estimated to generate $1,720,000 in annual sales, with costs of $630,000. The project requires an initial investment in net working capital of $270,000, and the fixed asset will have a market value of $210,000 at the end of the project. a. If the tax rate is 22 percent, what is the project’s Year 0 net cash flow? Year 1? Year 2? Year 3? (Do not round intermediate calculations and enter your answers in dollars, not millions of dollars, e.g., 1,234,567. A negative answer should be indicated by a minus sign.) b. If the required return is 10 percent, what is the project's NPV? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) a. whar are Years 0,1,2,3 cash flow seperately b. What is the NPV
Down Under Boomerang, Inc., is considering a new 3-year expansion project that requires an initial fixed asset investment of $2.3 million. The fixed asset will be |
a. | If the tax rate is 22 percent, what is the project’s Year 0 net cash flow? Year 1? Year 2? Year 3? (Do not round intermediate calculations and enter your answers in dollars, not millions of dollars, e.g., 1,234,567. A negative answer should be indicated by a minus sign.) |
b. |
If the required return is 10 percent, what is the project's NPV? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) |
a. whar are Years 0,1,2,3 cash flow seperately
b. What is the NPV
Trending now
This is a popular solution!
Step by step
Solved in 9 steps with 8 images