Direct Labor Cost Budget Ace Racket Company manufactures two types of tennis rackets, the Junior and Pro Striker models. The production budget for July for the two rackets is as follows:   Junior Pro Striker Production budget 1,500 units 6,200 units Both rackets are produced in two departments, Forming and Assembly. The direct labor hours required for each racket are estimated as follows:   Forming Department Assembly Department Junior 0.16 hour per unit 0.24 hour per unit Pro Striker 0.20 hour per unit 0.30 hour per unit The direct labor rate for each department is as follows: Forming Department $18.00 per hour Assembly Department $14.00 per hour Prepare the direct labor cost budget for July. Ace Racket Company Direct Labor Cost Budget For the Month Ending July 31   Forming Department Assembly Department Hours required for production:     Junior fill in the blank 1 fill in the blank 2 Pro Striker fill in the blank 3 fill in the blank 4 Total fill in the blank 5 fill in the blank 6 Hourly rate x $fill in the blank 7 x $fill in the blank 8 Total direct labor cost $fill in the blank 9 $fill in the blank 10

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
icon
Concept explainers
Question
  1. Direct Labor Cost Budget

    Ace Racket Company manufactures two types of tennis rackets, the Junior and Pro Striker models. The production budget for July for the two rackets is as follows:

      Junior Pro Striker
    Production budget 1,500 units 6,200 units

    Both rackets are produced in two departments, Forming and Assembly. The direct labor hours required for each racket are estimated as follows:

      Forming Department Assembly Department
    Junior 0.16 hour per unit 0.24 hour per unit
    Pro Striker 0.20 hour per unit 0.30 hour per unit

    The direct labor rate for each department is as follows:

    Forming Department $18.00 per hour
    Assembly Department $14.00 per hour

    Prepare the direct labor cost budget for July.

    Ace Racket Company
    Direct Labor Cost Budget
    For the Month Ending July 31
      Forming Department Assembly Department
    Hours required for production:    
    Junior fill in the blank 1 fill in the blank 2
    Pro Striker fill in the blank 3 fill in the blank 4
    Total fill in the blank 5 fill in the blank 6
    Hourly rate x $fill in the blank 7 x $fill in the blank 8
    Total direct labor cost $fill in the blank 9 $fill in the blank 10
  2.  
  3.  
 

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education