Determine the total estimated cost at completion for the project and the variance for each cost code.
8. A contractor has a contract to construct the sanitary sewer, water line, storm drain, and street lighting for a new subdivision. The contractor uses the cost codes in Figure 2-6. The original estimate for the sewer was $25,000, and a $3,200 change order has been approved to add a manhole. The sewer work has been completed by the contractor at a cost of $27,365. The original estimate for the waterline was $31,000, and no changes have been made to the budget. The costs to date for the waterline are $31,300 and it is estimated that it will take another $450 to complete the waterline. The water line is being installed by the contractor. The original estimate for the storm drain was $17,000, and no changes have been made to the budget. The contractor has paid $7,236 for materials and estimates that it will cost $9,764 to install the storm drain. The contractor will install the storm drain. The original estimate for the outside lighting was $23,600, and no changes have been made to the budget. The contractor has subcontracted the outside lighting for $23,600. The subcontractor has billed $11,230 for materials. Determine the total estimated cost at completion for the project and the variance for each cost code.
Please answer asap.if answered within 1hr ,it would be appreciable!!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps