Determine the balance on the job cost sheets for Jobs 275 and 310 at the end of May. b. Determine the cost per unit for Jobs 275 and 310 at the end of May
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
Job Costs
At the end of May, Lockmiller Company had completed Jobs 275 and 310. Job 275 is for 5,000 units, and Job 310 is for 2,000 units.
The following data relate to these two jobs:
On May 7, Lockmiller Company purchased on account 12,000 units of materials at $6 per unit. During May, raw materials were requisitioned for production as follows: 8,400 units for Job 275 at $6 per unit and 2,150 units for Job 310 at $4 per unit.
During May, Lockmiller Company accumulated 1,900 hours of direct labor costs on Job 275 and 2,600 hours on Job 310. The total direct labor was incurred at a rate of $34 per direct labor hour for Job 275 and $26 per direct labor hour for Job 310.
Lockmiller Company estimates that total
a. Determine the balance on the
b. Determine the cost per unit for Jobs 275 and 310 at the end of May. If required, round your answers to two decimal places.