Denver Enterprises recently used 14,000 labor hours to produce 7,500 completed units. According to manufacturing specifications, each unit is anticipated to take two hours to complete. The company's actual payroll cost amounted to OMR 158,200. If the standard labor cost per hour is OMR 11, Denver's labor efficiency variance is: Select one: a. 11,000 F b. 11,300 UNF c. 11,300 F d. 11,000 UNF
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Denver Enterprises recently used 14,000 labor hours to produce 7,500 completed units. According to manufacturing specifications, each unit is anticipated to take two hours to complete. The company's actual payroll cost amounted to OMR 158,200. If the
Trending now
This is a popular solution!
Step by step
Solved in 2 steps