Cumulative Average-Time Learning CurvePohlman Company makes aircraft engines. Pohlman has noticed that, in general, each new engine design is subject to an 80 percent learning rate. Assume that the first unit produced takes500 hours, and direct labor is paid an average of $30 per hour. Required:1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total pro-duction of: one engine, two engines, four engines, eight engines, sixteen engines, and thirty-two engines. (Round hour answers to two significant digits.) 2. What is the total labor cost if Pohlman manufactures the following number of engines: one,four, or sixteen? What is the average cost per engine for the following number of engines:one, four, or sixteen? (Round your answers to the nearest dollar.)3. What if Pohlman is preparing a bid to build 16 engines? Calculate budgeted labor cost for anengine design which Pohlman has built before (assume that 16 of these engines had been madepreviously and the first unit took 500 hours). Calculate budgeted labor cost for a new enginedesign that Pohlman’s workers have never made before (assume the first unit will take 500 hours).
Cumulative Average-Time Learning Curve
Pohlman Company makes aircraft engines. Pohlman has noticed that, in general, each new engine design is subject to an 80 percent learning rate. Assume that the first unit produced takes
500 hours, and direct labor is paid an average of $30 per hour.
Required:
1. Set up a table with columns showing: the cumulative number of units, cumulative average
time per unit in hours, and cumulative total time in hours. Show results by row for total pro-
duction of: one engine, two engines, four engines, eight engines, sixteen engines, and thirty-
two engines. (Round hour answers to two significant digits.)
2. What is the total labor cost if Pohlman manufactures the following number of engines: one,
four, or sixteen? What is the average cost per engine for the following number of engines:
one, four, or sixteen? (Round your answers to the nearest dollar.)
3. What if Pohlman is preparing a bid to build 16 engines? Calculate budgeted labor cost for an
engine design which Pohlman has built before (assume that 16 of these engines had been made
previously and the first unit took 500 hours). Calculate budgeted labor cost for a new engine
design that Pohlman’s workers have never made before (assume the first unit will take 500 hours).
Trending now
This is a popular solution!
Step by step
Solved in 4 steps