CU, Incorporated (CUI), produces copper contacts that it uses in switches and relays. CUI needs to determine the order quantity, Q, to meet the annual demand at the lowest cost. The price of copper depends on the quantity ordered. Here are price-break and other data for the problem: Price of copper $ 0.79 per pound up to 2,999 pounds $ 0.78 per pound for orders between 3,000 and 5,999 pounds $ 0.76 per pound for orders 6,000 pounds or greater Annual demand 50,000 pounds per year Holding cost 20 percent per unit per year of the price of the copper Ordering cost $ 30 Which quantity should be ordered?
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
CU, Incorporated (CUI), produces copper contacts that it uses in switches and relays. CUI needs to determine the order quantity, Q, to meet the annual demand at the lowest cost. The price of copper depends on the quantity ordered. Here are price-break and other data for the problem:
Price of copper | $ | 0.79 | per pound up to 2,999 pounds |
$ | 0.78 | per pound for orders between 3,000 and 5,999 pounds | |
$ | 0.76 | per pound for orders 6,000 pounds or greater | |
Annual demand | 50,000 | pounds per year | |
Holding cost | 20 | percent per unit per year of the price of the copper | |
Ordering cost | $ | 30 | |
Which quantity should be ordered?