Question
Critical path and project duration
The management of a factory is going to erect a maintenance building with a connecting electrical
generator (genset) and water tank. The activities, activity descriptions and estimated durations are
given in the following table:
Time
Activity Description
Predecessor
(weeks)
Earthworks/Land clearing
Foundation and building erection
a
3.
b
a
3.
Cable trench and elctrical cabling
b
d.
install generator (genset)
b
e
install tank
b
f
control panel and connection to genset
installation of pump to tank cw piping &
valve
e
2.
connect power supply
Finishing works (painting/labelling)
Testing and commissioning
d, f, g
b, d, e
2
i
3
j
f, h
24
Construct the network for this project, identify the critical path and determine the project duration time.
Transcribed Image Text:The management of a factory is going to erect a maintenance building with a connecting electrical generator (genset) and water tank. The activities, activity descriptions and estimated durations are given in the following table: Time Activity Description Predecessor (weeks) Earthworks/Land clearing Foundation and building erection a 3. b a 3. Cable trench and elctrical cabling b d. install generator (genset) b e install tank b f control panel and connection to genset installation of pump to tank cw piping & valve e 2. connect power supply Finishing works (painting/labelling) Testing and commissioning d, f, g b, d, e 2 i 3 j f, h 24 Construct the network for this project, identify the critical path and determine the project duration time.
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.