Crane Construction Co. has consistently used the percentage-of- completion method of recognizing revenue. During 2018, Crane entered into a fixed-price contract to construct an office building for $27,000,000. Information relating to the contract is as follows: At December 31 2018 2019 Percentage of completion 10% 40% Estimated total cost at completion $ 2,00,00,000 $ 2,14,00,000 Gross profit recognized (cumulative) $ 13,80,000 $ 33,10,000 Contract costs incurred during 2019 were: a. $5,250,000. b. $6,560,000. c. $8,190,000. d. $8,560,000.
Crane Construction Co. has consistently used the percentage-of- completion method of recognizing revenue. During 2018, Crane entered into a fixed-price contract to construct an office building for $27,000,000. Information relating to the contract is as follows: At December 31 2018 2019 Percentage of completion 10% 40% Estimated total cost at completion $ 2,00,00,000 $ 2,14,00,000 Gross profit recognized (cumulative) $ 13,80,000 $ 33,10,000 Contract costs incurred during 2019 were: a. $5,250,000. b. $6,560,000. c. $8,190,000. d. $8,560,000.
Financial Accounting Intro Concepts Meth/Uses
14th Edition
ISBN:9781285595047
Author:Weil
Publisher:Weil
Chapter8: Revenue Recognition, Receivables, And Advances From Customers
Section: Chapter Questions
Problem 48P
Related questions
Question
SOLVE TUTOR ASAP
![Crane Construction Co. has consistently used the percentage-of-
completion method of recognizing revenue. During 2018, Crane entered
into a fixed-price contract to construct an office building for
$27,000,000. Information relating to the contract is as follows:
At December 31
2018
2019
Percentage of completion
10%
40%
Estimated total cost at completion
$ 2,00,00,000
$ 2,14,00,000
Gross profit recognized (cumulative)
$ 13,80,000
$ 33,10,000
Contract costs incurred during 2019 were:
a. $5,250,000.
b. $6,560,000.
c. $8,190,000.
d. $8,560,000.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F71e93573-7763-4665-a6c0-a1a0fbb5db5a%2F970c622d-1e2b-47d6-b524-e74a8f0cc2d9%2Ftkl1xr8_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Crane Construction Co. has consistently used the percentage-of-
completion method of recognizing revenue. During 2018, Crane entered
into a fixed-price contract to construct an office building for
$27,000,000. Information relating to the contract is as follows:
At December 31
2018
2019
Percentage of completion
10%
40%
Estimated total cost at completion
$ 2,00,00,000
$ 2,14,00,000
Gross profit recognized (cumulative)
$ 13,80,000
$ 33,10,000
Contract costs incurred during 2019 were:
a. $5,250,000.
b. $6,560,000.
c. $8,190,000.
d. $8,560,000.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Intermediate Accounting: Reporting And Analysis](https://www.bartleby.com/isbn_cover_images/9781337788281/9781337788281_smallCoverImage.jpg)
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
![Intermediate Accounting: Reporting And Analysis](https://www.bartleby.com/isbn_cover_images/9781337788281/9781337788281_smallCoverImage.jpg)
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning