Craftmore Machining produces machine tools for the construction industry. The following details about overhead costs were taken from its company records. Production Activity Indirect Labor Indirect Materials Other Overhead Grinding $ 310,000 Polishing $ 145,000 Product modification 550,000 Providing power $ 260,000 System calibration 560,000 Additional information on the drivers for its production activities follows. Grinding 17,000 machine hours Polishing 17,000 machine hours Product modification 1,500 engineering hours Providing power 15,000 direct labor hours System calibration 200 batches Problem C-1A Part 3 Job 3175 Job 4286 Number of units 150 units 1,875 units Machine hours 350 MH 3,500 MH Engineering hours 30 eng. hours 30 eng. hours Batches 10 batches 30 batches Direct labor hours 520 DLH 4,680 DLH
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Craftmore Machining produces machine tools for the construction industry. The following details about
Production Activity | Indirect Labor | Indirect Materials | Other Overhead | |||||||||
Grinding | $ | 310,000 | ||||||||||
Polishing | $ | 145,000 | ||||||||||
Product modification | 550,000 | |||||||||||
Providing power | $ | 260,000 | ||||||||||
System calibration | 560,000 | |||||||||||
Additional information on the drivers for its production activities follows.
Grinding | 17,000 | machine hours |
Polishing | 17,000 | machine hours |
Product modification | 1,500 | engineering hours |
Providing power | 15,000 | direct labor hours |
System calibration | 200 | batches |
Problem C-1A Part 3
Job 3175 | Job 4286 | |||
Number of units | 150 | units | 1,875 | units |
Machine hours | 350 | MH | 3,500 | MH |
Engineering hours | 30 | eng. hours | 30 | eng. hours |
Batches | 10 | batches | 30 | batches |
Direct labor hours | 520 | DLH | 4,680 | DLH |