Contractor X is developing his bidding strategy against contractor Y. The ratio of Y's bid price to X's cost for the 30 previous bids in which contractor X has competed against contractor Y is given in the Table.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter13: Pricing Subcontractors' Work
Section: Chapter Questions
Problem 1RQ
icon
Related questions
Question
Contractor X is developing his bidding strategy
against contractor Y. The ratio of Y's bid price to
X's cost for the 30 previous bids in which contractor
X has competed against contractor Y is given in
the Table.
Ratio of Y's bid
Number of bids
Price of X's cost
1.02
6.
1.04
12
1.06
3.
1.10
6.
1.12
3
Based on the bidding behaviour of the contractor
Y, the probability of winning against contractor Y
at a mark up of 8% for the next project is
Transcribed Image Text:Contractor X is developing his bidding strategy against contractor Y. The ratio of Y's bid price to X's cost for the 30 previous bids in which contractor X has competed against contractor Y is given in the Table. Ratio of Y's bid Number of bids Price of X's cost 1.02 6. 1.04 12 1.06 3. 1.10 6. 1.12 3 Based on the bidding behaviour of the contractor Y, the probability of winning against contractor Y at a mark up of 8% for the next project is
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Bid package
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,