Construct a PERT network from the following table. Find the critical path and variance for each event, if to, tp, and to represent most optimistic, most pessimistic, and most likely times respectively. Activity 1-2 1-3 2-4 2-5 3-4 to tp tm 1 431 193 3 713 1537 275 7 3-6 4-5 4-6 5-7 922 223 663 6 6 123 6-7 7 6 2
Construct a PERT network from the following table. Find the critical path and variance for each event, if to, tp, and to represent most optimistic, most pessimistic, and most likely times respectively. Activity 1-2 1-3 2-4 2-5 3-4 to tp tm 1 431 193 3 713 1537 275 7 3-6 4-5 4-6 5-7 922 223 663 6 6 123 6-7 7 6 2
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
please solve it step by step
Construct a PERT network from the following table. Find the critical path and variance for eachevent, if ??, ??, ??? ?? represent most optimistic, most pessimistic, and most likely timesrespectively

Transcribed Image Text:Construct a PERT network from the following table. Find the critical path and variance for each
event, if to, tp, and to represent most optimistic, most pessimistic, and most likely times
respectively.
Activity 1-2 1-3 2-4 2-5 3-4
4
1
5
3
9
3
1
3
7
to
tp
tm
7
1
3
2
7
5
3-6 4-5 4-6 5-7
9
2
6
1
2
2
6
2
2
3
3
3
6-7
7
6
2
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 4 steps with 3 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning


Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning

Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education


Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning