Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value of $475,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $308 per ton. The engineering department estimates you will need an initial net working capital investment of $440,000. You require a return of 12 percent and face a tax rate of 23 percent on this project.    a. Suppose you’re confident about your own projections, but you’re a little unsure about Detroit’s actual machine screw requirement. What is the sensitivity of the project OCF to changes in the quantity supplied? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) b. What is the sensitivity of NPV to changes in quantity supplied? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) c. Given the sensitivity number you calculated, what is the minimum level of output below which you wouldn’t want to operate? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32)

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question

Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,100,000 and that variable costs should be $205 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value of $475,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $308 per ton. The engineering department estimates you will need an initial net working capital investment of $440,000. You require a return of 12 percent and face a tax rate of 23 percent on this project.

  

a.

Suppose you’re confident about your own projections, but you’re a little unsure about Detroit’s actual machine screw requirement. What is the sensitivity of the project OCF to changes in the quantity supplied? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

b. What is the sensitivity of NPV to changes in quantity supplied? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)
c. Given the sensitivity number you calculated, what is the minimum level of output below which you wouldn’t want to operate? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32)

  

 
Expert Solution
steps

Step by step

Solved in 5 steps with 15 images

Blurred answer
Knowledge Booster
Assets
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education