Cletus and Spike Company is implementing a Kanban system for a heated water bowl manufacturing line that produces 1,500 units in an eight-hour day. The heating element has a waiting time of 30 minutes and a processing time of one hour. The container size is 40 heating elements, and the safety factor is 15 percent. How many Kanban cards should be used?   a. 9     b. 12     c. 2     d. 27

Contemporary Marketing
18th Edition
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Louis E. Boone, David L. Kurtz
Chapter15: Distribution Channels And Supply Chain Management
Section15.4: Components Of The Supply Chain
Problem 1LO
icon
Related questions
Question

Cletus and Spike Company is implementing a Kanban system for a heated water bowl manufacturing line that produces 1,500 units in an eight-hour day. The heating element has a waiting time of 30 minutes and a processing time of one hour. The container size is 40 heating elements, and the safety factor is 15 percent. How many Kanban cards should be used?

  a. 9  
  b. 12  
  c. 2  
  d. 27

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Recommended textbooks for you
Contemporary Marketing
Contemporary Marketing
Marketing
ISBN:
9780357033777
Author:
Louis E. Boone, David L. Kurtz
Publisher:
Cengage Learning
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,