Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
You are working on a manufacturing project having a budget of PKR 3,600,000 and the expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve months. At the end of the fourth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project are giving the presentation to all the attendees and informed them that the project is on
- Calculate Cost and Schedule Variance
- What is SPI and CPI of the project?
- Estimate at completion and Estimated time to complete?
Trending now
This is a popular solution!
Step by step
Solved in 2 steps