c) What is the critical path for this project and how long is it?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
(c) What is the critical path for this project and how long is it?
![1. Applied Digital Solutions is expanding its operations to include a new product line for
manufacturing bioelectronic computer chip. The project for manufacturing this computer chip
has a high visibility. The following table lists the activities along with various probabilistic times
and the dependencies:
Times
Activity
Optimistic
Most Likely
Pessimistic
Immediate
Predecessor
Activities
А
2
3
4
В
6
7
8
C
13
20
1
3
4
1
E
10
11
12
1
F
4
8
4
G
11
13
15
4
H
5
7
4
3,6
2, 5, 8
7,9, 10
(Note that in the above table the predecessors are marked as A =1, B = 2, C = 3, D=4, etc.)
I
5
7
J
5
6
7
K
4
9.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fc4d5b940-4227-4804-a5a1-28e36f78c013%2Fae76a89f-353b-4fac-8e5a-0caf157bfdca%2F864kosn_processed.png&w=3840&q=75)
Transcribed Image Text:1. Applied Digital Solutions is expanding its operations to include a new product line for
manufacturing bioelectronic computer chip. The project for manufacturing this computer chip
has a high visibility. The following table lists the activities along with various probabilistic times
and the dependencies:
Times
Activity
Optimistic
Most Likely
Pessimistic
Immediate
Predecessor
Activities
А
2
3
4
В
6
7
8
C
13
20
1
3
4
1
E
10
11
12
1
F
4
8
4
G
11
13
15
4
H
5
7
4
3,6
2, 5, 8
7,9, 10
(Note that in the above table the predecessors are marked as A =1, B = 2, C = 3, D=4, etc.)
I
5
7
J
5
6
7
K
4
9.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.