Build-Rite Construction has received favorable publicity from guest appearances on a public TV home improvement program. Public TV programming decisions seem to be unpredictable, so Build-Rite cannot estimate the probability of continued benefits from its relationship with the show. Demand for home improvements next year may be either low or high. But Build-Rite must decide now whether to hire more employees, do nothing, or develop subcontracts with other home improvement contractors. Build-Rite has developed the following payoff table: Demand for Home Improvements Alternative Low Moderate High Hire ($250,000) $100,000 $625,000 Subcontract $100,000 $150,000 $415,000 Do nothing $50,000 $80,000 $300,000 Which alternative is best, according to each of thefollowing decision criteria?a. Maximinb. Maximaxc. Laplaced. Minimax regret
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Build-Rite Construction has received favorable publicity from guest appearances on a public TV home improvement program. Public TV programming decisions seem to be unpredictable, so Build-Rite cannot estimate the probability of continued benefits from its relationship with the show. Demand for home improvements next year may be either low or high. But Build-Rite must decide now whether to hire more employees, do nothing, or develop subcontracts with other home improvement contractors. Build-Rite has developed the following payoff table:
Demand for Home Improvements | |||
Alternative | Low | Moderate | High |
Hire | ($250,000) | $100,000 | $625,000 |
Subcontract | $100,000 | $150,000 | $415,000 |
Do nothing | $50,000 | $80,000 | $300,000 |
Which alternative is best, according to each of thefollowing decision criteria?
a. Maximin
b. Maximax
c. Laplace
d. Minimax regret