Brighton Manufacturing completed job #724 with a standard of 800 labor hours at a standard rate of $22.50 per hour. The job was actually completed in 850 hours with an average actual labor rate of $23.25 per hour. Calculate the labor efficiency (quantity) variance.

Managerial Accounting: The Cornerstone of Business Decision-Making
7th Edition
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Chapter10: Standard Costing And Variance Analysis
Section: Chapter Questions
Problem 58E: At the beginning of the year, Lopez Company had the following standard cost sheet for one of its...
icon
Related questions
Question

General Accounting question

Brighton Manufacturing completed job #724 with a standard of 800
labor hours at a standard rate of $22.50 per hour. The job was actually
completed in 850 hours with an average actual labor rate of $23.25 per
hour. Calculate the labor efficiency (quantity) variance.
Transcribed Image Text:Brighton Manufacturing completed job #724 with a standard of 800 labor hours at a standard rate of $22.50 per hour. The job was actually completed in 850 hours with an average actual labor rate of $23.25 per hour. Calculate the labor efficiency (quantity) variance.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning