Bridgenorth has undertaken a $5 million contract to repair a railway tunnel. The contract was signed on 1 April 20X8 and the work is expected to take two years. This is a contract where performance obligations are satisfied over time and progress in satisfying performance obligations is to be measured according to % of work completed as certified by a surveyor. Bridgenorth has an enforceable right to payment for performance completed to date. At 31 December 20X9 the details of the contract were as follows: 20X9 20X8 $ Total contract value 5,000,000 5,000,000 2,300,000 2,100,000 2,000,000 Costs to date 3,600,000 Estimated costs to completion 700,000 Work invoiced to date 3,000,000 Cash received to date 2,400,000 1,500,000 % certified complete 75% 40%

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

What is the profit recognised for the year ended 31 December 20X8?

Bridgenorth has undertaken a $5 million contract to repair a railway tunnel. The contract was signed on 1 April 20X8
and the work is expected to take two years. This is a contract where performance obligations are satisfied over time
and progress in satisfying performance obligations is to be measured according to % of work completed as certified
by a surveyor. Bridgenorth has an enforceable right to payment for performance completed to date.
At 31 December 20X9 the details of the contract were as follows:
20X9
20X8
$
$
5,000,000
Total contract value
5,000,000
Costs to date
3,600,000
2,300,000
Estimated costs to completion
700,000
2,100,000
Work invoiced to date
3,000,000
2,000,000
Cash received to date
2,400,000
1,500,000
% certified complete
75%
40%
Transcribed Image Text:Bridgenorth has undertaken a $5 million contract to repair a railway tunnel. The contract was signed on 1 April 20X8 and the work is expected to take two years. This is a contract where performance obligations are satisfied over time and progress in satisfying performance obligations is to be measured according to % of work completed as certified by a surveyor. Bridgenorth has an enforceable right to payment for performance completed to date. At 31 December 20X9 the details of the contract were as follows: 20X9 20X8 $ $ 5,000,000 Total contract value 5,000,000 Costs to date 3,600,000 2,300,000 Estimated costs to completion 700,000 2,100,000 Work invoiced to date 3,000,000 2,000,000 Cash received to date 2,400,000 1,500,000 % certified complete 75% 40%
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Accounting for Intangible assets
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education