Blue Construction Co. successfully tendered for a 3-year contract to erect some warehouse facilities in a new industrial zone. The following information has been provided. Contract price - $25 000 000 2022 2023 2024 Cost during year $ 4000 000 $8 000 000 $8 100 000 Estimated cost to complete 16 000 000 8 050 000 Progress billings to date 4 500 000 11 500 000 25 000 000 Cash collected to date 4 200 000 11 000 000 25 000 000 2022 i. Complete the following Workings Schedule. Cost to date Estimated cost to complete Total estimated cost 2023 2024 $ 6A +A +A Percentage complete (Round to nearest whole number) % Total contract price Total estimated cost Estimated gross profit or loss Revenue to recognize to date 69 +A Less Revenue previously recognized Revenue to recognize in year % % 69 EA 10 S

Financial Accounting Intro Concepts Meth/Uses
14th Edition
ISBN:9781285595047
Author:Weil
Publisher:Weil
Chapter8: Revenue Recognition, Receivables, And Advances From Customers
Section: Chapter Questions
Problem 35E
icon
Related questions
Question
Blue Construction Co. successfully tendered for a 3-year contract to erect some warehouse
facilities in a new industrial zone. The following information has been provided.
Contract price - $25 000 000
2022
2023
2024
Cost during year
$ 4000 000
$8 000 000
$8 100 000
Estimated cost to complete
16 000 000
8 050 000
Progress billings to date
4 500 000
11 500 000
25 000 000
Cash collected to date
4 200 000
11 000 000
25 000 000
2022
i. Complete the following Workings Schedule.
Cost to date
Estimated cost to complete
Total estimated cost
2023
2024
$
6A
+A
+A
Transcribed Image Text:Blue Construction Co. successfully tendered for a 3-year contract to erect some warehouse facilities in a new industrial zone. The following information has been provided. Contract price - $25 000 000 2022 2023 2024 Cost during year $ 4000 000 $8 000 000 $8 100 000 Estimated cost to complete 16 000 000 8 050 000 Progress billings to date 4 500 000 11 500 000 25 000 000 Cash collected to date 4 200 000 11 000 000 25 000 000 2022 i. Complete the following Workings Schedule. Cost to date Estimated cost to complete Total estimated cost 2023 2024 $ 6A +A +A
Percentage complete (Round
to nearest whole number)
%
Total contract price
Total estimated cost
Estimated gross profit or loss
Revenue to recognize to date
69
+A
Less Revenue previously
recognized
Revenue to recognize in year
%
%
69
EA
10
S
Transcribed Image Text:Percentage complete (Round to nearest whole number) % Total contract price Total estimated cost Estimated gross profit or loss Revenue to recognize to date 69 +A Less Revenue previously recognized Revenue to recognize in year % % 69 EA 10 S
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning