"Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year: Manufacturing overhead Direct labor Department Fabricating Machining Assembly Total Plant $365,750 $ 418,000 $ 94,050 $ 877,800 $ 209,000 $ 104,500 $ 313,500 $ 627,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct labor Manufacturing overhead Fabricating $3,900 $4,600 ? Department Machining $ 200 $ 500 ? Assembly $ 2,300 $ 7,100 ? Total Plant $ 6,400 $12,200 ? Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a.Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a.What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

The first part of this was answered. I just need 2B, 4A, and 4B answered 

"Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're
either too high to get the job or too low to make any money on half the jobs we bid."
Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a
plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to
jobs. The following estimates were made at the beginning of the year:
Manufacturing overhead
Direct labor
Fabricating
Department
Machining
Assembly
Total Plant
$ 365,750 $ 418,000 $ 94,050 $ 877,800
$ 209,000 $ 104,500 $ 313,500 $ 627,000
Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing
costs in the three departments as follows:
Direct materials
Direct labor
Manufacturing overhead
Fabricating
$ 3,900
$ 4,600
?
Department
Machining
$ 200
$ 500
?
Assembly
$2,300
$ 7,100
?
Required:
1. Using the company's plantwide approach:
a. Compute the plantwide predetermined rate for the current year.
b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.
2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined
overhead rates based on direct labor cost. Under these conditions:
a.Compute the predetermined overhead rate for each department for the current year.
b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.
Complete this question by entering your answers in the tabs below.
Total Plant
$ 6,400
$12,200
?
4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied
overhead).
a.What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate?
b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?
< Required 1A
Required 1A Required 1B Required 2A Required 2B Required 4A Required 4B
Using the company's plantwide approach, compute the plant wide predetermined rate for the current year.
Predetermined overhead rate
% of direct labor cost
Required 1B >
Transcribed Image Text:"Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $3,000. It seems we're either too high to get the job or too low to make any money on half the jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year: Manufacturing overhead Direct labor Fabricating Department Machining Assembly Total Plant $ 365,750 $ 418,000 $ 94,050 $ 877,800 $ 209,000 $ 104,500 $ 313,500 $ 627,000 Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows: Direct materials Direct labor Manufacturing overhead Fabricating $ 3,900 $ 4,600 ? Department Machining $ 200 $ 500 ? Assembly $2,300 $ 7,100 ? Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a.Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Complete this question by entering your answers in the tabs below. Total Plant $ 6,400 $12,200 ? 4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a.What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? < Required 1A Required 1A Required 1B Required 2A Required 2B Required 4A Required 4B Using the company's plantwide approach, compute the plant wide predetermined rate for the current year. Predetermined overhead rate % of direct labor cost Required 1B >
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Pricing Decisions
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education