Black Builders Co. is a construction firm that uses the percentage of completion method of recognizing income. On August 2, 2019, a contract to build an office condominium was obtained at a price of P8,700,000. Below are the data pertaining to this contract: 2019 2020 Estimated cost at completion P6,525,000 P6,960,000 Cumulative income recognized 435,000 1,044,000 Percentage of completion 15% 65% Based on the above information, what is the amount cost of contract incurred during the year ended December 31, 2020? a. 3,741,000 b. 4,611,000 c. 4,176,000
Black Builders Co. is a construction firm that uses the percentage of completion method of recognizing income. On August 2, 2019, a contract to build an office condominium was obtained at a price of P8,700,000. Below are the data pertaining to this contract: 2019 2020
Estimated cost at completion P6,525,000 P6,960,000
Cumulative income recognized 435,000 1,044,000
Percentage of completion 15% 65%
Based on the above information, what is the amount cost of contract incurred during the year ended December 31, 2020?
a. 3,741,000
b. 4,611,000
c. 4,176,000
d. 3,545,250