Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2018 and completed in 2019. Cost and other data are presented below: 2018 2019 $ 450,000 $1,100,000 1,050,000 0 400,000 1,400,000 Billings during the year Cash collections during the year 300,000 1,500,000 Costs incurred during the year Estimated costs to complete Requirements: a. Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Compute the amount of gross profit recognized during 2018 and 2019 b. Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Prepare all journal entries to record costs, billings, collections, and profit recognition. c. Assume that Beavis recognizes revenue upon completion of the project. Compute the amount of gross profit recognized during 2018 and 2019. d. Assume that Beavis recognizes revenue upon completion of the project. Prepare all journal entries to record costs, billings, collections, and profit recognition.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2018 and completed in 2019. Cost and other data are presented below:
2018
2019
$ 450,000 $1,100,000
1,050,000
Costs incurred during the year
Estimated costs to complete
Billings during the year
Cash collections during the year
0
400,000 1,400,000
300,000 1,500,000
Requirements:
a. Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Compute the amount of gross profit recognized during 2018 and 2019
b. Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Prepare all journal entries to record costs, billings, collections, and profit recognition.
c. Assume that Beavis recognizes revenue upon completion of the project. Compute the amount of gross profit recognized during 2018 and 2019.
d. Assume that Beavis recognizes revenue upon completion of the project. Prepare all journal entries to record costs, billings, collections, and profit recognition.
Transcribed Image Text:Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2018 and completed in 2019. Cost and other data are presented below: 2018 2019 $ 450,000 $1,100,000 1,050,000 Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 0 400,000 1,400,000 300,000 1,500,000 Requirements: a. Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Compute the amount of gross profit recognized during 2018 and 2019 b. Assume that Beavis recognizes revenue on this contract over time according to percentage of completion. Prepare all journal entries to record costs, billings, collections, and profit recognition. c. Assume that Beavis recognizes revenue upon completion of the project. Compute the amount of gross profit recognized during 2018 and 2019. d. Assume that Beavis recognizes revenue upon completion of the project. Prepare all journal entries to record costs, billings, collections, and profit recognition.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Impairment of Assets
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education