Based on the project's performance complete the risk assessment chart below by rating each risk factor as follows: • High, medium, or low in terms of its potential impact • High, medium, or low in terms of its probability of occurrence

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
Scenario
You are the project manager working on a Market Mailing project. The client informed your project team
during the project planning phase that the project must be completed on time in order to sync with the launch
of the new product. Also, the client informed you and the team that there is no cash reserve for the project so
the project has to be completed within budget. Below is the status update that two project team members
(Jennifer and Ben) put together. Based on the project's performance to date, complete the Rating Project
Risk exercise on the next page.
Task| Budgeted Actual Percent
works
Estimate Planned Planned Actual Projected| Planned
to
Actual
Resource Resource
Utilization Utilization
works
end date
work
complete complete date
start
start
date
end
cost
cost
date
to
date
60
hours
I $600
50
hours
I $500
June 15 March June 15
120
hours /
$1200
120
hours /
$1200
A
30%
90 hours
March
25%
30%
I $900
15
30
May 15
April
8
B
30%
April 1
May 30
30%
60 hours
I $600
50%
Rating Project Risk
Based on the project's performance complete the risk assessment chart below by rating each risk factor as
follows:
• High, medium, or low in terms of its potential impact
• High, medium, or low in terms of its probability of occurrence
Project Risk Items
Potential
Probability
Overall Risk Risk Score Justification
Impact
of
(H/M/L)
Statement
(H /M/L)
Occurrence
(H /M/L)
Completing Task A
over the $1,200 budget
Completing Task A
after the scheduled
end date of June 15
Completing Task B
over the $1,200 budget
Completing Task B
after the scheduled
end date of May 30
Extract the combined effect of those two values, combined with your judgment, and score each risk factor as
high, medium, or low overall. Justify your scores using the data provided above.
Transcribed Image Text:Scenario You are the project manager working on a Market Mailing project. The client informed your project team during the project planning phase that the project must be completed on time in order to sync with the launch of the new product. Also, the client informed you and the team that there is no cash reserve for the project so the project has to be completed within budget. Below is the status update that two project team members (Jennifer and Ben) put together. Based on the project's performance to date, complete the Rating Project Risk exercise on the next page. Task| Budgeted Actual Percent works Estimate Planned Planned Actual Projected| Planned to Actual Resource Resource Utilization Utilization works end date work complete complete date start start date end cost cost date to date 60 hours I $600 50 hours I $500 June 15 March June 15 120 hours / $1200 120 hours / $1200 A 30% 90 hours March 25% 30% I $900 15 30 May 15 April 8 B 30% April 1 May 30 30% 60 hours I $600 50% Rating Project Risk Based on the project's performance complete the risk assessment chart below by rating each risk factor as follows: • High, medium, or low in terms of its potential impact • High, medium, or low in terms of its probability of occurrence Project Risk Items Potential Probability Overall Risk Risk Score Justification Impact of (H/M/L) Statement (H /M/L) Occurrence (H /M/L) Completing Task A over the $1,200 budget Completing Task A after the scheduled end date of June 15 Completing Task B over the $1,200 budget Completing Task B after the scheduled end date of May 30 Extract the combined effect of those two values, combined with your judgment, and score each risk factor as high, medium, or low overall. Justify your scores using the data provided above.
Expert Solution
Step 1

Risk Assessment:

Risk assessment is the act of assessing the possible or prospective risks that may arise in a project. Risk assessment analyses the potential hazards and implements various techniques to eliminate them.

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Risk Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education